Converted · ground-floor conversion · Lone Mountain/USF

2000 Grove St

Completed Feb 2025+1 unit on this lot · now 71 permit

Revision to pa#: 2018-0509-8704. Install new heat pump system (split) for new ADU unit#a at ground floor. Pa#: 2018-0509-8704 called for direct-vent wall furnace for bedroom use.

filed Oct 2024issued Oct 2024 · permit wait 3 dayscompleted Feb 2025 · built in 5 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$15,000
declared on the ADU permit
Permit wait
3 days
filed → issued
Build time
5 months
issued → completed
Builder
No contractor listed

Permits in this project

PermitWhatWhenDeclared
ADU permitRevision to pa#: 2018-0509-8704. Install new heat pump system (split) for new ADU unit#a at ground floor. Pa#: 2018-0509-8704 called for direct-vent wall furnace for bedroom use.
202410042365
filed Oct 2024 · issued Oct 2024 · done Feb 2025$15kcity record

These permits also cite 201805098704, which the city filed before our records begin.

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 1189, lot 002D
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map