Converted · ground-floor conversion · Bayview Hunters Point

2008A Keith St

Completed May 2025+0 units on this lot · now 13 permits

Convert existing rooms to be new ADU at ground flr per state program (including 2 bedrooms, 1 bath and kitchen.

filed May 2024issued Jan 2025 · permit wait 8 monthscompleted May 2025 · built in 4 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$50,000
declared on the ADU permit
Permit wait
8 months
filed → issued
Build time
4 months
issued → completed
Builder
No contractor listed

Permits in this project

PermitWhatWhenDeclared
ADU permitConvert existing rooms to be new ADU at ground flr per state program (including 2 bedrooms, 1 bath and kitchen.
202401234472
filed May 2024 · issued Jan 2025 · done May 2025$50kcity record
ElectricalKitchen remodeling at existing space.
EW202501133428
Jan 13, 2025 → Mar 24, 2025—
PlumbingWork category: 2pa; add a new kitchen at existing space.
PW20250113252
Jan 13, 2025 → Mar 24, 2025—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 5386, lot 039
Why we call it an ADU
Two independent model reviewers agreed the permit creates an ADU: “"convert (e) rooms to be new adu at ground flr per state program (including 2 bedrooms, 1 bath and kitchen"; use 1 family dwelling \u2192 2 family dwelling”
Claim this project or house

City record of the ADU permitProperty Information Map