Converted · garage conversion · Portola
201 Girard St
In progress+1 unit on this lot · now 16 permits
Garage to ADU conversion. Change of use and occupancy of existing group u detached garage to a group r-3 one unit ADU at the rear of the lot with no changes to the existing group r-3 building at the front of the lot.
filed May 2021issued Apr 2022 · permit wait 11 months4 years 7 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$200,000
declared on the ADU permit
Permit wait
11 months
filed → issued
Build time
in progress
issued → completed
Builder
No contractor listed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Garage to ADU conversion. Change of use and occupancy of existing group u detached garage to a group r-3 one unit ADU at the rear of the lot with no changes to the existing group r-3 building at the front of the lot. 202105049767 | filed May 2021 · issued Apr 2022 | $200k | city record |
| Electrical | Rewire electrical. New plugs, lights, switches. E202204149602 | Apr 14, 2022 → Sep 13, 2022 | — | |
| Electrical | Pv on roof 3. 16kw dc 3. 8kw ac 8 modules - 8 roof-mounted solar pv modules, 395 watts per module, 1 interactive inverter, total no. Of rating 3. 8 kw. EW202305151116 | May 15, 2023 → Oct 5, 2023 | — | |
| Electrical | Pv on roof 3. 555kw dc 3. 8kw ac 9 modules - 9 roof-mounted solar pv modules, 395 watts per module, 1 interactive inverter, total no. Of rating 3. 8 kw. EW202308303540 | Aug 30, 2023 → Oct 10, 2023 | — | |
| Electrical | Address correction: unit 2: pv on roof 3. 16kw dc 3. 8kw ac 8 modules - 8 roof-mounted solar pv modules, 395 watts per module, 1 interactive inverter, total no. Of rating 3. 8 kw. E202308319091 | Aug 31, 2023 → Oct 5, 2023 | — | |
| Plumbing | New plumbing for ADU. PP20220414296 | Apr 14, 2022 → Sep 2, 2022 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 5981, lot 024
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.