Converted · legalization · Inner Sunset
2011 17th Ave
Completed Aug 2022+1 unit on this lot · now 23 permits
1)legalization of an unauthorized unit as 2011a 17th ave consisting of 3 ground floor rooms; replace of extg ango alley entry in kind. 2) 1 hour seperation between unit and garage. 3) sprinkler in unit under seperate permit.
filed Sep 2021issued Feb 2022 · permit wait 4 monthscompleted Aug 2022 · built in 7 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$40,000
declared on the ADU permit
Permit wait
4 months
filed → issued
Build time
7 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | 1)legalization of an unauthorized unit as 2011a 17th ave consisting of 3 ground floor rooms; replace of extg ango alley entry in kind. 2) 1 hour seperation between unit and garage. 3) sprinkler in unit under seperate permit. 202109249107 · North South Construction INC | filed Sep 2021 · issued Feb 2022 · done Aug 2022 | $40k | city record |
| Revision | Revision to pa# 202109249107. ADU wall unit heater to be reused to electric. 202204051595 · cites 202109249107 · North South Construction INC | filed Apr 2022 · issued Apr 2022 · done Aug 2022 | — | city record |
| Electrical | New wiring of ADU. EW202204263088 | Apr 26, 2022 → Jul 12, 2022 | — |
Trade permits show what work was done and when; the city does not record who pulled them.