Converted · legalization · Sunset/Parkside

2025 Quintara St

Completed May 2026+1 unit on this lot · now 24 permits

Legalization of existing unauthorized dwelling unit under ordinance 43-14. New unit #2 on 1st floor 419 SF.

filed Dec 2024issued Jul 2025 · permit wait 7 monthscompleted May 2026 · built in 10 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$94,000
declared on the ADU permit
Permit wait
7 months
filed → issued
Build time
10 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitLegalization of existing unauthorized dwelling unit under ordinance 43-14. New unit #2 on 1st floor 419 SF.
202409181009 · Mak Tai Lam
filed Dec 2024 · issued Jul 2025 · done May 2026$94kcity record
ElectricalWorking in the basement. Install 10 lights, 8 switches, 7 circuit breakers, 2 fans, and 50 amp sub panel.
EW202512291754
Dec 29, 2025 → Apr 9, 2026—
PlumbingWork category: 2pa; install 2 sinks, 1 stove, 1 bathtub, 1 toilet, and 1 gas.
PW20251229520
Dec 29, 2025 → Apr 16, 2026—
PlumbingWork category: 1m; install new furnace.
PMW20260211545
Feb 11, 2026 → Apr 16, 2026—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 2188, lot 052
Why we call it an ADU
Two independent model reviewers agreed the permit creates an ADU: “"legalization of existing unauthorized dwelling unit under ordinance 43-14. new unit #2 on 1st floor 419 sf."”
Claim this project or house

City record of the ADU permitProperty Information Map