Converted · legalization · Bayview Hunters Point
2058 Thomas Ave
Completed Oct 2024+1 unit on this lot · now 23 permits
Abate nov#202200095. Legalize kitchen setup, all work done in the ground floor unit. Include lighting, electrical outlets, switches, ventilation fans, hvac sytem, plumbing work. Replace & upsize electrical service main panel to 200amps, install 100 amps sub panel in the lower lvel proposed ADU.
filed Jun 2023issued Jun 2024 · permit wait 1 yearcompleted Oct 2024 · built in 4 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$175,450
declared on the ADU permit
Permit wait
1 year
filed → issued
Build time
4 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Abate nov#202200095. Legalize kitchen setup, all work done in the ground floor unit. Include lighting, electrical outlets, switches, ventilation fans, hvac sytem, plumbing work. Replace & upsize electrical service main panel to 200amps, install 100 amps sub panel in the lower lvel proposed ADU. 202306130006 · J & L Construction Company | filed Jun 2023 · issued Jun 2024 · done Oct 2024 | $175k | city record |
| Electrical | Installing lighting, installing 100 amps sub panel in lower level for proposed ADU. E202407235781 | Jul 23, 2024 → Oct 23, 2024 | — | |
| Plumbing | Rough plumbing for lower floor ADU. PP20240723022 | Jul 23, 2024 → Oct 24, 2024 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 5384A, lot 022
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.