Converted · garage conversion · Potrero Hill

2105 20th St

Completed Nov 2024+1 unit on this lot · now 413 permits

Convert existing two-car garage area to ground floor ADU looking onto rear yard and 20th street. New ADU to be entirely within existing building envelope. New ADU to be type va construction and be sprinklered per cbc 903. 3. 1. 1 or 903. 3. 1. 2. New ADU to contain: living room, kitchen, (1) bath, (1) bedroom.

filed Nov 2020issued Oct 2021 · permit wait 11 monthscompleted Nov 2024 · built in 3 years 1 month
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$219,128
declared across 4 permits: the ADU permit plus its sub-permits
Permit wait
11 months
filed → issued
Build time
3 years 1 month
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitConvert existing two-car garage area to ground floor ADU looking onto rear yard and 20th street. New ADU to be entirely within existing building envelope. New ADU to be type va construction and be sprinklered per cbc 903. 3. 1. 1 or 903. 3. 1. 2. New ADU to contain: living room, kitchen, (1) bath, (1) bedroom.
202011199318 · Ben Hardy & Company
filed Nov 2020 · issued Oct 2021 · done Nov 2024$180kcity record
SprinklersInstall new fire sprinkler per nfpa 13. For the ground floor ADU only, including 2" underground fire service: total=9 heads.
202401244554 · Madden Plumbing LLC
filed Jan 2024 · issued Feb 2024 · done Oct 2024$11kcity record
Related permitReplace existing fire alarm system with notification to comply withsffd sec. 1103. 6. 1. Install facu, aes radio, smoke detectors, pull stations, monitor modules, wireless gateway, & horn strobes. Install wired & wireless lf sounders in potential sleeping areas in existing residential units to comply.
202408148609 · San Francisco Fire Protection
filed Aug 2024 · issued Aug 2024 · done Oct 2024$23kcity record
RevisionRevision: 1) new egress and common path of travel to new gate location. 2) inclusion of new rear yard slab. Revision for permit 202011199318.
202411124769 · cites 202011199318 · Ben Hardy & Company
filed Nov 2024 · issued Nov 2024 · done Nov 2024$5,000city record
ElectricalRun new electrical throughout the upstairs unit.
E202112307591
Dec 30, 2021 → Aug 7, 2023—
ElectricalNew ADU, unit #4, 1 bedroom, bath, kitchen and living room wired with new sub panel.
EW202401045995
Jan 4, 2024 → Jul 3, 2024—
ElectricalOnline electrical permit: 60 of buildings of 6 dwelling units or less. Fire alarm system upgrade with lf sounders add-on in new ADU and existing units. .
E202403283394
Mar 28, 2024—
ElectricalOnline electrical permit: 60 of buildings of 6 dwelling units or less. Replace existing fas with notif to comply with sffc sec. 1103. 7. 6. 1 sleeping ordinance.
E202408226443
Aug 22, 2024 → Oct 9, 2024—
PlumbingWork category: 1m; installation of a direct-vent gas fireplace with a direct-vent flue terminated to minimum code height above the roofline.
PMW20220629767
Jun 29, 2022 → Sep 14, 2022—
PlumbingWork category: 1m; install one heat pump system.
PMW20240111795
Jan 11, 2024 → Jul 2, 2024—
PlumbingWork category: 2pa; above slab plumbing install for ADU.
PW20240209501
Feb 9, 2024 → Aug 15, 2024—
PlumbingWork category: 4pa; provide and install overhead fire sprinkler system throughout ADU, includes underground service.
PW20240221756
Feb 21, 2024 → Sep 19, 2024—
PlumbingWork category: 1p; reference permit number 20211230266. Finish plumbing - new plumbing for kitchen, washer dryer, bathrooms and new plumbing in bathroom units one, two and three. Shower pan also included.
PW20240523025
May 23, 2024 → May 28, 2024—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 4094, lot 001
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map