Converted · ground-floor conversion · Inner Richmond
211 Cornwall St
Completed Oct 2022+2 units on this lot · now 149 permits
Addition of two (2) accsessory dwelling units to an existing twelve (12) unit building per ordinance 162-16 for a total of fourteen (14) units. The two (2) proposed dwellings are located within the existing building envelope at the first floor.
filed Feb 2021issued Dec 2021 · permit wait 10 monthscompleted Oct 2022 · built in 10 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$426,000 for 2 ADUs
one permit, 2 units; not a per-unit price
Permit wait
10 months
filed → issued
Build time
10 months
issued → completed
Builder
Rivera M Construction INCAlso on this project: City Fire Protection, Crime Watch Security Sys Llc
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Addition of two (2) accsessory dwelling units to an existing twelve (12) unit building per ordinance 162-16 for a total of fourteen (14) units. The two (2) proposed dwellings are located within the existing building envelope at the first floor. 202102195037 · Rivera M Construction INC | filed Feb 2021 · issued Dec 2021 · done Oct 2022 | $340k | city record |
| Sprinklers | Install (46) sprinklers troughout ground floor per nfpa 13. Underground per nfpa 24; referencing 202102195037. 202203109678 · cites 202102195037 · City Fire Protection | filed Mar 2022 · issued Mar 2022 · done Oct 2022 | $20k | city record |
| Sprinklers | Upgrade existing f/a system to comply with sffc section 1103. 7. 6. 1, includes sprinkler monitoring. Ref bpa#202102195031 & 202203109678. 202207208959 · Crime Watch Security Sys Llc | filed Jul 2022 · issued Jul 2022 · done Oct 2022 | $30k | city record |
| Sprinklers | Upgrade existing fire alarm system to comply with sffc section 1103. 7. 6. 1 and include sprinkler monitoring. 202208190929 · Crime Watch Security Sys Llc | filed Aug 2022 · issued Aug 2022 | $36k | city record |
| Electrical | Wire 2 new ADU units on ground floor, add 2 meters and 2 panels, install ufer ground. EW202201250985 | Jan 25, 2022 → Sep 2, 2022 | — | |
| Electrical | Modification of an existing fire alarm system by upgrading the fire panel, update all existing devices to be compatible with new facp, add monitor modules to monitor all sprinkler water flow and tamper devices, and provide low frequency sounders in all sleeping areas to meet 75db at pillow to comply with sffd bulletin 1103. 7. 6. 1. EW202204283125 | Apr 28, 2022 → Oct 5, 2022 | — | |
| Plumbing | Install 2 kitchens and 2 bathrooms for new ADU. PP20220218216 | Feb 18, 2022 → Sep 21, 2022 | — | |
| Plumbing | Work category: 4pa; install (46) new sprinklers throughout ground floor per nfpa #13 & underground per nfpa #24. PW20220425844 | Apr 25, 2022 → Sep 16, 2022 | — | |
| Plumbing | Units a&b: install (2) hvac systems (hot/cold). PM20220516885 | May 16, 2022 → Sep 7, 2022 | — |
These permits also cite 202102195031, which the city filed before our records begin.
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 1430, lot 046
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.