Converted · ground-floor conversion · Bernal Heights

212 Genebern Way

In progress+1 unit on this lot · now 29 permits

Renovation of existing home. On main level, enlarged kitchen to include bar seating and open walls to family and dining rooms. Attached bath added to 2 bedrooms, and maintain 1 bedroom and full bath. New direct vent fireplace in living room. On lower level adding: staircase from main level, newlaundry,.

filed Oct 2022issued Mar 2024 · permit wait 1 year 5 months2 years 8 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$963,808 + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
1 year 5 months
filed → issued
Build time
in progress
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitRenovation of existing home. On main level, enlarged kitchen to include bar seating and open walls to family and dining rooms. Attached bath added to 2 bedrooms, and maintain 1 bedroom and full bath. New direct vent fireplace in living room. On lower level adding: staircase from main level, newlaundry,.
202210174502 · Kasas Builders INC
filed Oct 2022 · issued Mar 2024$962kcity record
RevisionRevision to pa # 2022-1017-4502: reduction in scope. Deck size is smaller. Install door #8 in lieu of window 14. Install new 45 min rated door in lieu of door #4 at common hall.
202512051068 · cites 202210174502 · Kasas Builders INC
filed Dec 2025 · issued Dec 2025$2,000city record
AddressAddressing permit only: add the address 209 genebern way. Link to apn 5840/003. Ref ADU pa # 2022-1017-4502.
202604219796 · cites 202210174502 · Kasas Builders INC
filed Apr 2026 · issued Apr 2026—city record
AddressAddressing permit: create the address 210 genebern way. Ref pa #202210174502.
202608277316 · cites 202210174502
· issued Aug 2026—city record
ElectricalRenovation of existing home. Rewire house including new attached ADU and upgrade main panel from 100 amps to 400 amps to seperate 200 amp meters. Total 400 amps.
E202505212604
May 21, 2025—
ElectricalSolarapp+ approval: sa20251017-2454-487-10166-a - installing 14 roof-mounted solar pv modules, 430 watts per module, total no. Of rating 6. 02 kw. Including 1 energy storage unit, of 240 vdc, 15 a, with 13. 5 kwh each in capacity. Installing (14) hanwha q. Tron blk m-g2+.
E202510176461
Oct 17, 2025—
ElectricalSolarapp+ approval: sa20260428-2454-106-10166-a - installing 8 roof-mounted solar pv modules, 430 watts per module, total no. Of rating 3. 44 kw. Including 1 energy storage unit, of 240 vdc, 15 a, with 13. 5 kwh each in capacity. Installing (8) hanwha q. Tron blk m-g2+ 4.
E202604280597
Apr 28, 2026—
PlumbingNew heat pump heating system. New ducting for main house and ADU.
PM20251205237
Dec 5, 2025—
PlumbingTo renew pp20250521389 (renovation of existing kitchen and bathrooms. Add new bath in bedroom 3 with shower plus new attached ADU on lower level shower and new stackable washer/dryer. Seperate laundry room for upper level. 2 shower pans. ).
PP20260522189
May 22, 2026—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 5840, lot 003
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map