Converted · ground-floor conversion · Bayview Hunters Point

225A Wheeler Ave

Completed Apr 2026+1 unit on this lot · now 22 permits

Convert 1/f to ADU. No change to layout. Add tub to make full bath, add windows to new bedroom, add windows to new living room, new kitchen, new bedroom. No change to s.

filed Jul 2025issued Oct 2025 · permit wait 3 monthscompleted Apr 2026 · built in 6 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$175,000
declared on the ADU permit
Permit wait
3 months
filed → issued
Build time
6 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitConvert 1/f to ADU. No change to layout. Add tub to make full bath, add windows to new bedroom, add windows to new living room, new kitchen, new bedroom. No change to s.
202410314113 · Iron Rock Construction INC
filed Jul 2025 · issued Oct 2025 · done Apr 2026$175kcity record
ElectricalUnit 225a- for final inspection only.
E202602118910
Feb 11, 2026 → Feb 17, 2026—
2 other permits on this lot during the project, not counted
OtherTo obtain final inspection for work approved under pa# 202411205435. All work is approved.
202603117383 · Iron Rock Construction INC
filed Mar 2026 · issued Mar 2026 · done Apr 2026—city record
OtherRevision to permits 202407307607 and 202506259488 - as a reduction in the scope of work to not include the foundation upgrade at the rear portion of the structure. Existing foundation to remain in-kind.
202604239957 · Iron Rock Construction INC
filed Apr 2026 · issued Apr 2026 · done Apr 2026—city record

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 5070, lot 023
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map