Converted · ground-floor conversion · North Beach
24 Jasper Pl
Completed Sep 2022+1 unit on this lot · now 101 permit
The scope of the project is to add one new accessory dwelling unit to the existing ground level as per ordinance no. 162-16.
filed Jan 2021issued Mar 2022 · permit wait 1 year 2 monthscompleted Sep 2022 · built in 6 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$70,000
declared on the ADU permit
Permit wait
1 year 2 months
filed → issued
Build time
6 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | The scope of the project is to add one new accessory dwelling unit to the existing ground level as per ordinance no. 162-16. 202101283530 · Perez Construction LLC | filed Jan 2021 · issued Mar 2022 · done Sep 2022 | $70k | city record |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 0116, lot 040
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.