Converted · ground-floor conversion · North Beach

24 Jasper Pl

Completed Sep 2022+1 unit on this lot · now 101 permit

The scope of the project is to add one new accessory dwelling unit to the existing ground level as per ordinance no. 162-16.

filed Jan 2021issued Mar 2022 · permit wait 1 year 2 monthscompleted Sep 2022 · built in 6 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$70,000
declared on the ADU permit
Permit wait
1 year 2 months
filed → issued
Build time
6 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitThe scope of the project is to add one new accessory dwelling unit to the existing ground level as per ordinance no. 162-16.
202101283530 · Perez Construction LLC
filed Jan 2021 · issued Mar 2022 · done Sep 2022$70kcity record

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 0116, lot 040
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map

Converted · ground-floor conversion ADU at 24 Jasper Pl · MiCasa