Attached · Pacific Heights
2417 Green St
In progress+1 unit on this lot · now 29 permits
Horizontal addition. Expansion of existing garage in basement level, 1st, 2nd, 3rd & 4th story horizontal rear yard addition; alterations to existing front facade; excavation & full foundation replacement; interior remodel; ADU at 1/f sb-9.
filed Apr 2017issued Dec 2023 · permit wait 6 years 8 months2 years 11 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$1,563,248 + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
6 years 8 months
filed → issued
Build time
in progress
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Horizontal addition. Expansion of existing garage in basement level, 1st, 2nd, 3rd & 4th story horizontal rear yard addition; alterations to existing front facade; excavation & full foundation replacement; interior remodel; ADU at 1/f sb-9. 201704285244 · Durkin INC | filed Apr 2017 · issued Dec 2023 | $1.5M | city record |
| Revision | Revision to 201704285244-s2. Updaete to northeast corner of 4th floor and roof. Portion of roof removed to accomodate new corner window with reducing habitable area by 7sf. 202504114238 · cites 201704285244 · Durkin INC | filed Apr 2025 · issued Apr 2025 | $5,000 | city record |
| Sprinklers | Residential fire sprinklers system- 56 sprinklers. 2" underground-25 ft. 202507160876 · Madden Plumbing LLC | filed Jul 2025 · issued Sep 2025 | $44k | city record |
| Revision | Revision to bpa#2017-0428-5244(s2). Ref bpa#2025-0411-4238: including revised joist depths at the first floor, third floor, and roof, and revised beam framing at northeast corner of roof. 202508294212 · cites 201704285244 · Durkin INC | filed Aug 2025 · issued Sep 2025 | — | city record |
| Revision | The proposed project generally consists of the addition of a roof deck to the rear 4th sloor and motarized operable skylight assembly to an existing 4 story over basement single family residence. Revision to bpa 201704285244 addendum 1 & 2. 202602095520 · cites 201704285244 · Durkin INC | filed Apr 2026 · issued Aug 2026 | $25k | city record |
| Electrical | Whole house remodel with new service. EW202510210268 | Oct 21, 2025 | — | |
| Plumbing | Work category: 2pb; renewal of expired plumbing permit pw20240418193: rough in and trim out of 4 baths 2 half baths, 2 kitchens, 2 laundry. PW20251030231 | Oct 30, 2025 | — | |
| Plumbing | Work category: 4pa; provide approximately 66 fire sprinkler heads. Includes bfp and fdc. PW20260427459 | Apr 27, 2026 | — | |
| Plumbing | Work category: 2pa; install 3 hydronic fan coil units with condensate drainage. One heat pump. Radiant tubing in pex on all floors as well as all mechanical room equipment. PW20260430549 | Apr 30, 2026 | — |
1 other permit on this lot during the project, not counted
| Other | Interior work only: remove plaster, replace with drywall throughout. All work in kind. 202402065337 · Durkin INC | filed Feb 2024 · issued Feb 2024 | $35k | city record |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 0560, lot 028
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.