Converted · ground-floor conversion · Marina
2436 Greenwich St
Completed Jun 2023+1 unit on this lot · now 55 permits
Addition of one ADU unit at the ground floor under the local ADU program.
filed Jan 2022issued Sep 2022 · permit wait 7 monthscompleted Jun 2023 · built in 9 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$120,900
declared across 3 permits: the ADU permit plus its sub-permits
Permit wait
7 months
filed → issued
Build time
9 months
issued → completed
Builder
Achill Beg Construction INCAlso on this project: North Star Plumbing & Fire Protection INC, San Francisco Fire Protection
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Addition of one ADU unit at the ground floor under the local ADU program. 202201196250 · Achill Beg Construction INC | filed Jan 2022 · issued Sep 2022 · done Jun 2023 | $90k | city record |
| Sprinklers | Installaton of fire sprinkler system per nfpa 13 in new ADU; includes underground; ref 202201196250. 202210214890 · cites 202201196250 · North Star Plumbing & Fire Protection INC | filed Oct 2022 · issued Oct 2022 · done Jun 2023 | $28k | city record |
| Related permit | New f/s water flloor & supervisory system. Install new control panel, radio, smoke detector & pull station due to new ADU on ground floor. Install modules to tie-in flow & teamper switche to new panel. Ref pa 202201196250 & 202210214890. 202305107484 · cites 202201196250 · San Francisco Fire Protection | filed May 2023 · issued May 2023 · done Jun 2023 | $3,000 | city record |
| Electrical | New f/s water flloor & supervisory system. Install new control panel, radio, smoke detector & pull station due to new ADU on ground floor. Install modules to tie-in flow & teamper switche to new panel. Ref pa 202201196250 & 202210214890. EW202305221296 | May 22, 2023 → Jun 13, 2023 | — | |
| Plumbing | Work category: 4pa; installation of sprinkler system inside the ADU on the first floor. PW20221024983 | Oct 24, 2022 → May 1, 2023 | — |
1 other permit on this lot during the project, not counted
| Other | Replace stucco at front facade in kind. Approx 600 sq ft. 202301120061 · Achill Beg Construction INC | filed Jan 2023 · issued Feb 2023 · done Jun 2023 | $5,400 | city record |
Trade permits show what work was done and when; the city does not record who pulled them.