Detached · Sunset/Parkside

2538A Great Hwy

Completed Jan 2026+1 unit on this lot · now 114 permits

Addition of one detached ADU unit at the rear of the building under the state ADU program.

filed Mar 2022issued Apr 2023 · permit wait 1 year 1 monthcompleted Jan 2026 · built in 2 years 10 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$142,415
declared across 3 permits: the ADU permit plus its sub-permits
Permit wait
1 year 1 month
filed → issued
Build time
2 years 10 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAddition of one detached ADU unit at the rear of the building under the state ADU program.
202203018927 · K N A B Builders
filed Mar 2022 · issued Apr 2023 · done Jan 2026$120kcity record
SprinklersTi- 202203018927- install overhead fire sprinkler system.
202409120581 · cites 202203018927 · Control Fire INC
filed Sep 2024 · issued Sep 2024 · done Dec 2025$13kcity record
RevisionRef 2022-0301-8927 revision to pa 2024-0912-0581 (rear building only) as builts to show current underground work. Riser location changed & copper pipe install.
202410082500 · cites 202203018927 · Control Fire INC
filed Oct 2024 · issued Oct 2024 · done Dec 2025$9,606city record
RevisionRear building - revision #3 to permit 202410082500, re-routing of underground. Ref permits 202409120581, 202203018927.
202510066765 · cites 202203018927 · Control Fire INC
filed Oct 2025 · issued Oct 2025 · done Dec 2025—city record
ElectricalRelocate main panel, rewire entire house and new ADU at the back of the house (per plan).
E202407035390
Jul 3, 2024 → Nov 20, 2025—
ElectricalInstall new electrical lights and oultlets per plan new subpanel and new electrical hybrid water heater.
E202409166915
Sep 16, 2024 → Dec 22, 2025—
ElectricalNew 6 panel pv system with 415 watt maxeon panels. 6 enphase microinverters. 1 franklin 15 bess - 6 roof-mounted solar pv modules, 415 watts per module, 6 interactive inverter, total no. Of rating 3. 8 kw.
EW202409271403
Sep 27, 2024—
ElectricalNew 3. 32 kw pv system with 15 kwh franklin bess - 8 roof-mounted solar pv modules, 415 watts per module, 1 interactive inverter, total no. Of rating 3. 8 kw.
EW202410181929
Oct 18, 2024 → Jun 30, 2025—
PlumbingWork category: 1p; provide and install*state** hybrid 80 gal heat pump water heater(hpwh).
PW20240926892
Sep 26, 2024 → Sep 5, 2025—
PlumbingWork category: 1m; install split heat pump: 25vna4 - infinity variable speed heat pump with greenspeed technology infinity series 17-24 seer variable speed heat pump - 3 ton.
PMW20250224300
Feb 24, 2025 → Aug 29, 2025—
PlumbingWork category: 1p; provide and install rudd standard 40-gallon heat pump water heater.
PW20250812272
Aug 12, 2025 → Sep 5, 2025—
PlumbingWork category: 1m; provide and install carrier ductless mini split system. This includes (1) one outdoor heat pump and (1) indoor high wall-mounted units.
PMW20250812273
Aug 12, 2025 → Aug 29, 2025—
PlumbingWork category: 4pa; fire sprinkler system.
PW20251114568
Nov 14, 2025 → Dec 3, 2025—
PlumbingRenewal of permit # pp2020703709: add new underground blumbing for new ADU, relocate new bathrooms and kitchen per plan and add new bathroom in the garage level.
PP20251205241
Dec 5, 2025 → Dec 19, 2025—
1 other permit on this lot during the project, not counted
OtherRef 202308033695 & 202503122086 - underpinning below existing north property line footing required due to work at property line.
202503192529 · Norwood Construction INC
filed Mar 2025 · issued Mar 2025 · done May 2025$5,000city record

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 2448, lot 003H
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map