Convert part of (3)existing ground floor commercial spaces into (3)new residential units. Proposed conversion takes place within the existing building envlope - no expansion of existing envelope.

filed Dec 2020issued Jul 2022 · permit wait 1 year 7 monthscompleted Jan 2024 · built in 1 year 6 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$436,341 for 3 ADUs + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
1 year 7 months
filed → issued
Build time
1 year 6 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitConvert part of (3)existing ground floor commercial spaces into (3)new residential units. Proposed conversion takes place within the existing building envlope - no expansion of existing envelope.
202012261737 · Pineda Construction INC
filed Dec 2020 · issued Jul 2022 · done Jan 2024$350kcity record
SprinklersInstall (79) sprinklers throughout g/f per nfpa 13, 13-r and underground per nfpa 24. Ref pa 202012261737.
202209152532 · cites 202012261737 · City Fire Protection
filed Sep 2022 · issued Sep 2022 · done Nov 2024$43kcity record
SprinklersInstallation of a new sprinkler monitoring system. Ref sprinkler permit 202209152532.
202210194676 · Crime Watch Security Sys Llc
filed Oct 2022 · issued Oct 2022$4,000city record
AddressPer pa #202012261737, add address for three ADU to apn 3637/027 as: 2645a 2645b, 2645c mission st.
M1229490 · cites 202012261737
filed Nov 2022 · issued Nov 2022—city record
SprinklersFire alarm system replacement and new lf horns to meet 2022 sffc 1103. 7. 6. 1. Install new mini module to sprinkler water flow & temper valve fro central system monitorying.
202304125540 · C & E Electric & Fire Alarm Services
filed Apr 2023 · issued Nov 2023 · done Nov 2023$39kcity record
ElectricalNew fan and light receptacle in new bathroom.
E202208021682
Aug 2, 2022 → Oct 25, 2022—
ElectricalNew fan and light receptacle in new bathroom.
E202208021680
Aug 2, 2022 → Oct 31, 2023—
ElectricalNew fan and light receptacle in new bathroom.
E202208021681
Aug 2, 2022 → Oct 25, 2022—
Electrical3 new residential units split from existing commercial space per plans under pa202012261737. New plugs, lights, switches, subpanesl, bathroom exhaust fans and otr exhaust fans.
E202208021683
Aug 2, 2022—
ElectricalNew fire alarm panel, smoke detector, pull station, horn strobes, wireless communicator.
EW202311105103
Nov 10, 2023 → Nov 20, 2023—
PlumbingInstall two furnaces int he 2 new commerical units and install 3 furnaces for the 3 new residential units.
PM20220802294
Aug 2, 2022 → Jan 23, 2024—
PlumbingNew 3 residential units. 2 units 1-1/2 bath & ktichen with 4 burner gas stoves. 1 studio unit: 1 bathroom & kitchen with 4 burner gas stoves. 6 new water heaters. 3 commerical ada bathrooms.
PP20220802293
Aug 2, 2022 → Jan 17, 2024—
PlumbingWork category: 4pb; install (79) new sprinklers throughout ground floor retail space per nfpa #13. New ADU per nfpa 13-r. Underground per nfpa #24.
PW20221006530
Oct 6, 2022 → Aug 7, 2023—
1 other permit on this lot during the project, not counted
OtherMinor t. I. To existing g/f spaces. Work to include 2 offices, community room & small kitchenette. Existing ada entries, ada bathrooms, hvac, f/s approved under pa202012261737.
202209202751 · Pineda Construction INC
filed Sep 2022 · issued Sep 2022 · done Nov 2022$70kcity record

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 3637, lot 027
Why we call it an ADU
Two independent model reviewers agreed the permit creates an ADU: “"convert part of (3)(e) ground fl commercial spaces into (3)(n) residential units"; units 8 → 11; companion permit M1229490: "add address for three adu to apn 3637/027"”
Claim this project or house

City record of the ADU permitProperty Information Map