Converted · garage conversion · Mission
2676 Folsom St
Completed Apr 2023+2 units on this lot · now 69 permits
Priority processing - 100% affordable housing. Convert existing ground level garage space to create (2) new accessory dwelling units per ordinance 162-17, including foundation replacement and other necessary structural, mechanical, electrical and plumbing scope.
filed Dec 2020issued Jul 2022 · permit wait 1 year 8 monthscompleted Apr 2023 · built in 9 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$532,600 for 2 ADUs
one permit, 2 units; not a per-unit price
Permit wait
1 year 8 months
filed → issued
Build time
9 months
issued → completed
Builder
Blackline ConstructionAlso on this project: All Star Fire Protection LLC, Crime Watch Security Sys Llc
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Priority processing - 100% affordable housing. Convert existing ground level garage space to create (2) new accessory dwelling units per ordinance 162-17, including foundation replacement and other necessary structural, mechanical, electrical and plumbing scope. 202012019960 · Blackline Construction | filed Dec 2020 · issued Jul 2022 · done Apr 2023 | $500k | city record |
| Sprinklers | Install new fire sprinlkers throughout gr floor per nfp a 13. Including 2" dedicated service per nfpa 24. Ref 202012019960. 202208150510 · cites 202012019960 · All Star Fire Protection LLC | filed Aug 2022 · issued Aug 2022 · done Apr 2023 | $29k | city record |
| Sprinklers | Installation of a new sprinkler monitoring system. Ref sprinkler permit 202208150510. 202303133529 · Crime Watch Security Sys Llc | filed Mar 2023 · issued Mar 2023 · done Jun 2023 | $4,000 | city record |
| Electrical | Electrical for garage ADU #2. E202208161927 | Aug 16, 2022 → Feb 24, 2023 | — | |
| Electrical | Electrical for garage ADU #1. E202208161926 | Aug 16, 2022 → Jun 22, 2023 | — | |
| Electrical | Installation of a sprinkler monitoring system. EW202303279971 | Mar 27, 2023 → Apr 3, 2023 | — | |
| Plumbing | Install new fire sprinklers through and ground floor per nfpa is including 2" dedicated service per nfpa 24. PP20220816530 | Aug 16, 2022 → Mar 30, 2023 | — | |
| Plumbing | Plumbing for (2) ADU's. PP20220816538 | Aug 16, 2022 → Feb 27, 2023 | — | |
| Plumbing | Add mini split to ADU. PM20221219647 | Dec 19, 2022 → Feb 27, 2023 | — |
1 other permit on this lot during the project, not counted
| Other | Temporary shoring for foundation replacement. 202208019657 · Blackline Construction | filed Aug 2022 · issued Aug 2022 · done Apr 2023 | $55k | city record |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 3638, lot 012
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.