Converted · ground-floor conversion · Sunset/Parkside

2709 43rd Ave

Completed Aug 2022+1 unit on this lot · now 24 permits

Comply with nov #202183969 work in 1st floor only: ADU 1)seperate entrance created to 1st floor. 2) installing kitchen sink, cabinets, counter stove with hood. 3) convert home office to new bed room.

filed Jan 2022issued May 2022 · permit wait 4 monthscompleted Aug 2022 · built in 3 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$5,000
declared on the ADU permit
Permit wait
4 months
filed → issued
Build time
3 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitComply with nov #202183969 work in 1st floor only: ADU 1)seperate entrance created to 1st floor. 2) installing kitchen sink, cabinets, counter stove with hood. 3) convert home office to new bed room.
202201206319 · Wong Kyle Construction
filed Jan 2022 · issued May 2022 · done Aug 2022$5,000city record
ElectricalAdd a new receptacle for furnace. (reference #202201206319).
E20220610737
Jun 10, 2022—
ElectricalInstall new wire for ADU kitchen. Install a sub-panel for ADU kitchen. 1 switches, 7 receptacles, 1 fan, 1 dishwasher, 1 garbage disposal, 1 range, 6 circuits. Ref building pa# 202201206319.
E202207131283
Jul 13, 2022 → Jul 19, 2022—
PlumbingAdd a new furnace of 45000 btu. Existing ducts reconnect to new furnace.
PM20220610387
Jun 10, 2022 → Aug 2, 2022—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 2512, lot 001A
Why we call it an ADU
Two independent model reviewers agreed the permit creates an ADU: “"adu 1)seperate entrance created to 1st floor. 2) installing kitchen sink, cabinets, counter stove with hood"; units 1 \u2192 2, use 1 family dwelling \u2192 2 family dwelling”