Converted · ground-floor conversion · Mission
2730 23rd St
Completed Aug 2026+3 units on this lot · now 411 permits
Add (3) new ADU per plannning code section 207(c)(4). 1st floor: add (3) new units include bedrooms, bathrooms, living and kitchen. Retrofit seismic work under pa#202211146459.
filed Feb 2023issued Apr 2024 · permit wait 1 year 2 monthscompleted Aug 2026 · built in 2 years 5 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$661,900 for 3 ADUs
one permit, 3 units; not a per-unit price
Permit wait
1 year 2 months
filed → issued
Build time
2 years 5 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Add (3) new ADU per plannning code section 207(c)(4). 1st floor: add (3) new units include bedrooms, bathrooms, living and kitchen. Retrofit seismic work under pa#202211146459. 202302172173 · Home Run INC | filed Feb 2023 · issued Apr 2024 · done Aug 2026 | $600k | city record |
| Revision | Revision to approved pa# 202302172173. Replace or sister new stud to existing wall per plan. 202410243705 · cites 202302172173 | filed Oct 2024 · issued Nov 2024 | $5,000 | city record |
| Sprinklers | New sprinkler system install and 2" dedicated water service underground. 202505237156 · Cali Pro Fire Protection | filed May 2025 · issued May 2025 · done Apr 2026 | $57k | city record |
| Electrical | Unit #2: 1 kitchen & 1. 5 bath. Sub panel. Ref pa#202302172173. E202407115525 | Jul 11, 2024 → Feb 11, 2026 | — | |
| Electrical | Unit #1: main panel 200 amp, 1 kitchen & 1 bath. 1 subpanel. Ref pa# 202302172173. E202407115523 | Jul 11, 2024 → Feb 11, 2026 | — | |
| Electrical | Unit #3 1 kitchen, 2 baths & subpanel. E202407165594 | Jul 16, 2024 → Feb 11, 2026 | — | |
| Electrical | Unit #4 1 kitchen, 2 bath with new subpanel. E202407165595 | Jul 16, 2024 → Feb 17, 2026 | — | |
| Electrical | New 400 amps mian service. E202506303571 | Jun 30, 2025 → Feb 11, 2026 | — | |
| Electrical | Witness test. 1 hour. E202603249830 | Mar 24, 2026 → Apr 3, 2026 | — | |
| Plumbing | Unit# 1: 1 kitchen & 1 bath. Unit #2: 1 kitchen & 1. 5 bath. Unit #3: 1 kitchen & 2 baths. Unit #4: 1 kitchen & 2 baths with underground. 4 gas meters. PP20240711817 | Jul 11, 2024 → Feb 9, 2026 | — | |
| Plumbing | Installing 36k btu ducted fan coil and heat pump system. One multi zone mini split system 24k but with 3 wall mount fan coils 12k and 6k btu. One mini split system 18k heat pump with 2 wall mount 12k and 6k. One mini split system 18k heat pump with 2 wall mount 12k and 6k btu. PM20250626103 | Jun 26, 2025 → Feb 11, 2026 | — |
3 other permits on this lot during the project, not counted
| Other | Replace and repair damaged siding on historical building (replace with in kind siding) (street visible). 202505297517 · Home Run INC | filed May 2025 · issued May 2025 · done Apr 2026 | $20k | city record |
| Other | To obtain final inspection for work aproved under pa# 202405091824 and 202410243705. All work is complete. 202605131197 | filed May 2026 · issued May 2026 · done Jul 2026 | — | city record |
| Other | To obtain final inspection for work aproved under pa# 202211096199 and 202211146459. All work is complete. 202605131199 | filed May 2026 · issued May 2026 · done Aug 2026 | — | city record |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 4153, lot 017
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.