Converted · ground-floor conversion · Mission

2730 23rd St

Completed Aug 2026+3 units on this lot · now 411 permits

Add (3) new ADU per plannning code section 207(c)(4). 1st floor: add (3) new units include bedrooms, bathrooms, living and kitchen. Retrofit seismic work under pa#202211146459.

filed Feb 2023issued Apr 2024 · permit wait 1 year 2 monthscompleted Aug 2026 · built in 2 years 5 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$661,900 for 3 ADUs
one permit, 3 units; not a per-unit price
Permit wait
1 year 2 months
filed → issued
Build time
2 years 5 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAdd (3) new ADU per plannning code section 207(c)(4). 1st floor: add (3) new units include bedrooms, bathrooms, living and kitchen. Retrofit seismic work under pa#202211146459.
202302172173 · Home Run INC
filed Feb 2023 · issued Apr 2024 · done Aug 2026$600kcity record
RevisionRevision to approved pa# 202302172173. Replace or sister new stud to existing wall per plan.
202410243705 · cites 202302172173
filed Oct 2024 · issued Nov 2024$5,000city record
SprinklersNew sprinkler system install and 2" dedicated water service underground.
202505237156 · Cali Pro Fire Protection
filed May 2025 · issued May 2025 · done Apr 2026$57kcity record
ElectricalUnit #2: 1 kitchen & 1. 5 bath. Sub panel. Ref pa#202302172173.
E202407115525
Jul 11, 2024 → Feb 11, 2026—
ElectricalUnit #1: main panel 200 amp, 1 kitchen & 1 bath. 1 subpanel. Ref pa# 202302172173.
E202407115523
Jul 11, 2024 → Feb 11, 2026—
ElectricalUnit #3 1 kitchen, 2 baths & subpanel.
E202407165594
Jul 16, 2024 → Feb 11, 2026—
ElectricalUnit #4 1 kitchen, 2 bath with new subpanel.
E202407165595
Jul 16, 2024 → Feb 17, 2026—
ElectricalNew 400 amps mian service.
E202506303571
Jun 30, 2025 → Feb 11, 2026—
ElectricalWitness test. 1 hour.
E202603249830
Mar 24, 2026 → Apr 3, 2026—
PlumbingUnit# 1: 1 kitchen & 1 bath. Unit #2: 1 kitchen & 1. 5 bath. Unit #3: 1 kitchen & 2 baths. Unit #4: 1 kitchen & 2 baths with underground. 4 gas meters.
PP20240711817
Jul 11, 2024 → Feb 9, 2026—
PlumbingInstalling 36k btu ducted fan coil and heat pump system. One multi zone mini split system 24k but with 3 wall mount fan coils 12k and 6k btu. One mini split system 18k heat pump with 2 wall mount 12k and 6k. One mini split system 18k heat pump with 2 wall mount 12k and 6k btu.
PM20250626103
Jun 26, 2025 → Feb 11, 2026—
3 other permits on this lot during the project, not counted
OtherReplace and repair damaged siding on historical building (replace with in kind siding) (street visible).
202505297517 · Home Run INC
filed May 2025 · issued May 2025 · done Apr 2026$20kcity record
OtherTo obtain final inspection for work aproved under pa# 202405091824 and 202410243705. All work is complete.
202605131197
filed May 2026 · issued May 2026 · done Jul 2026—city record
OtherTo obtain final inspection for work aproved under pa# 202211096199 and 202211146459. All work is complete.
202605131199
filed May 2026 · issued May 2026 · done Aug 2026—city record

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 4153, lot 017
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map