Converted · legalization · Excelsior
274 Naples St
Completed Dec 2022+1 unit on this lot · now 21 permit
Comply with complaint# 20196481. Add one ADU per ord# 95-17, legalize kitchen at ground flr.
filed Oct 2019issued Nov 2022 · permit wait 3 yearscompleted Dec 2022 · built in 35 days
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$20,000
declared on the ADU permit
Permit wait
3 years
filed → issued
Build time
35 days
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Comply with complaint# 20196481. Add one ADU per ord# 95-17, legalize kitchen at ground flr. 201910316112 · W F Construction Co | filed Oct 2019 · issued Nov 2022 · done Dec 2022 | $20k | city record |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 6008, lot 014
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.