Completed Jul 2025+1 unit on this lot9 permits

Addition of one detached ADU unit at the rear of the building under the state ADU program.

filed Jan 2022issued Feb 2023 · permit wait 1 year 2 monthscompleted Jul 2025 · built in 2 years 4 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$188,569
declared across 3 permits: the ADU permit plus its sub-permits
Permit wait
1 year 2 months
filed → issued
Build time
2 years 4 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAddition of one detached ADU unit at the rear of the building under the state ADU program.
202201065469 · Y W Builders INC
filed Jan 2022 · issued Feb 2023 · done Jul 2025$150kcity record
SprinklersInstall new fire sprinkler system per nfpa 13-d throughout new ADU including 1" underground service per nfda24. Ref#: 202201065469 s1.
202410183229 · cites 202201065469 · Wd Fire Protection INC
filed Oct 2024 · issued Oct 2024 · done Mar 2025$29kcity record
RevisionRevision to pa # 2024-1018-3229 added separate drawing of domestic water for ADU.
202412066342 · Wd Fire Protection INC
filed Dec 2024 · issued Dec 2024 · done Mar 2025$10kcity record
ElectricalAddition of (1) detached ADU.
E202408066055
Aug 6, 2024 → Mar 27, 2025—
ElectricalPv plan # 6959 14 pv modules x 430 watts / 1000 = 6. 02 kw. (batteries (1) powerwall 3 13. 5 kwh) please, notify district inspector at the start of work at 415. 558. 3369.
E202504111568
Apr 11, 2025 → Apr 28, 2025—
PlumbingAddition of (1) detached ADU. Furnace and related hvac work.
PM20240806258
Aug 6, 2024 → Mar 26, 2025—
PlumbingAddition of (1) detached ADU. Underground plumbing. (1) shower pan installation.
PP20240806257
Aug 6, 2024 → Mar 20, 2025—
PlumbingWork category: 2pb; plumbing work for a detached ADU consisting of 1 kitchen, 1 bathroom with a showerpan, and 1 laundry room. There will be underground plumbing work performed.
PW20240918688
Sep 18, 2024—
PlumbingWork category: 4pa; installation of new fire sprinkler system per nfpa 13d throughout the new ADU for a total of 7 sprinkler heads with 2'' underground fire service per nfpa24.
PW20241025682
Oct 25, 2024 → Mar 20, 2025—

Trade permits show what work was done and when; the city does not record who pulled them.