Converted · legalization · Pacific Heights

2742A Bush St

Completed Sep 2025+1 unit on this lot · now 36 permits

Comply with planning enforcement case# 2018-009028cua. Legalize unauthorized dwelling unit on 1st floor as an ADU in the front building per government code #68652. 2. Verify existing structure complies with lateral force oer 2019 sfebc 506. 4. 3 change of occupancy from r-3 to r-2. New heat pump in side yd.

filed Feb 2021issued Aug 2023 · permit wait 2 years 7 monthscompleted Sep 2025 · built in 2 years 1 month
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$220,000
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
2 years 7 months
filed → issued
Build time
2 years 1 month
issued → completed
Builder
No contractor listed

Permits in this project

PermitWhatWhenDeclared
ADU permitComply with planning enforcement case# 2018-009028cua. Legalize unauthorized dwelling unit on 1st floor as an ADU in the front building per government code #68652. 2. Verify existing structure complies with lateral force oer 2019 sfebc 506. 4. 3 change of occupancy from r-3 to r-2. New heat pump in side yd.
202102013767
filed Feb 2021 · issued Aug 2023 · done Sep 2025$150kcity record
RevisionRevision to pa# 202102013767: to comply with nov 201724854 - remove and infill existing window adjacent to exit passageway. New door b/w bathroom and closet. Remove existing door b/w hall and closet. New radiant heat new wall mounted combo smoke and carbon alarm. New combo exhaust and iaq fan. Delete requiremen.
202406053750 · cites 202102013767
filed Jun 2024 · issued Aug 2024 · done Sep 2025—city record
RevisionRevision to pa# 202102013767: to expand scope of work of foundation per engineer inspection and plan - save kitchen and bath as much as possible and to replace undersized wooden support beam with steel beam. (ref pa# 202406053750).
202410243680 · cites 202102013767
filed Oct 2024 · issued Oct 2024 · done Sep 2025$70kcity record
ElectricalRewire for entire unit.
EW202411272738
Nov 27, 2024 → May 29, 2025—
PlumbingWork category: 2pb; remodel bathroom and laundry.
PW20241105913
Nov 5, 2024 → Aug 6, 2025—
PlumbingWork category: 1p; radiant heating panels installation over the concrete slab, combination boiler, pvc flue.
PW20250225361
Feb 25, 2025 → Jun 3, 2025—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 1048, lot 045
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map