Detached · Pacific Heights
2765A Vallejo St
In progress+1 unit on this lot · now 15 permits
Construction of 1 detached ADU: 2 story type v-b ~1000sf.
filed Sep 2025issued Dec 2025 · permit wait 3 months11 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$312,500
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
3 months
filed → issued
Build time
in progress
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Construction of 1 detached ADU: 2 story type v-b ~1000sf. 202508213594 · Ggd INC | filed Sep 2025 · issued Dec 2025 | $308k | city record |
| Revision | Revision to pa 202508213594 structural work only. Change plywood shear wall to concrete. Modify concrete slab to adjust to field conditions. No exterior work. Revision requested by building inspector. 202603308512 · cites 202508213594 · Ggd INC | filed Mar 2026 · issued Apr 2026 | $4,500 | city record |
| Electrical | New circuits, switches, lights, fixtures, receptacles, per architectural drawings. EW202512161572 | Dec 16, 2025 | — | |
| Plumbing | Work category: 4pa; renewal for expired permit ref #pw20230627062 & #pw20220523725. PW20260319483 | Mar 19, 2026 | — | |
| Plumbing | Work category: 1m; mitsubishi multiport heat pump hvac system. PMW20260727794 | Jul 27, 2026 | — |
1 other permit on this lot during the project, not counted
| Other | Solar permit: mounted: roof, ballasted: n, including 2 energy storage unit, of 240 vac, with 13. 5 kwh each in capacity, ess units will not be closer than 3 feet | installation of energy storage system. S20251209382 · Nissi Electric | filed Dec 2025 · issued Jan 2026 | $30k | city record |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 0959, lot 017A
- Why we call it an ADU