Converted · legalization · Outer Mission

279 Ocean Ave

In progress+1 unit on this lot · now 57 permits

Response to notice of violation [nov] #2018. 2. 8. 811. To legalize an unauthorized dwelling unit at the ground floor commercial space per ordinance 43-14.

filed Feb 2020issued Sep 2021 · permit wait 1 year 7 months5 years 2 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$101,051
declared across 3 permits: the ADU permit plus its sub-permits
Permit wait
1 year 7 months
filed → issued
Build time
in progress
issued → completed
Builder
No contractor listed

Permits in this project

PermitWhatWhenDeclared
ADU permitResponse to notice of violation [nov] #2018. 2. 8. 811. To legalize an unauthorized dwelling unit at the ground floor commercial space per ordinance 43-14.
202002124318
filed Feb 2020 · issued Sep 2021$85kcity record
SprinklersInstall new fire sprinkler system throughout gr floor ADU unit per nfpa 13 including dedicated underground 2" fire service per nfpa 24 total 12 sprinklers. Ref pa 202002124318.
202110210919 · cites 202002124318 · Chan Gary Plumbing
filed Oct 2021 · issued Oct 2021$12kcity record
SprinklersInstallation of a new sprinkler monitoring system. Ref 202110210919.
202208291494 · Crime Watch Security Sys Llc
filed Aug 2022 · issued Aug 2022 · done Nov 2022$4,000city record
ElectricalInstall new wiring for stove and new fire system.
EW202201100665
Jan 10, 2022 → Feb 7, 2023—
ElectricalInstallation of a sprinkler monitoring system.
EW202210136591
Oct 13, 2022 → Oct 26, 2022—
PlumbingWork category: 1p; install water heater.
PW20230124186
Jan 24, 2023 → Jan 25, 2023—
PlumbingWork category: 4pa; for final inspection.
PW20230125217
Jan 25, 2023 → Jan 26, 2023—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 6952, lot 007
Why we call it an ADU
Two independent model reviewers agreed the permit creates an ADU: “"to legalize an unauthorized dwelling unit at the ground floor commercial space per ordinance 43-14"; units 4 → 5”
Claim this project or house

City record of the ADU permitProperty Information Map