Converted · ground-floor conversion · Presidio Heights
2B Lupine Ave
Completed Feb 2026+1 unit on this lot · now 23 permits
Develope existing utility basement of the existing single family dwelling into an attached ADU per state program: install new kitchen with a living, dining, kitchen, room. Install new bedroom with full bath. Install detached pre-fab 4'6" x 5' x 6'ht utility shed at existing exterior concrete patio.
filed Feb 2024issued Sep 2024 · permit wait 7 monthscompleted Feb 2026 · built in 1 year 5 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$105,953
declared on the ADU permit
Permit wait
7 months
filed → issued
Build time
1 year 5 months
issued → completed
Builder
No contractor listed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Develope existing utility basement of the existing single family dwelling into an attached ADU per state program: install new kitchen with a living, dining, kitchen, room. Install new bedroom with full bath. Install detached pre-fab 4'6" x 5' x 6'ht utility shed at existing exterior concrete patio. 202402206131 | filed Feb 2024 · issued Sep 2024 · done Feb 2026 | $106k | city record |
| Electrical | One bedroom, kitchen, bathroom- sub panel 60amp. E202411088093 | Nov 8, 2024 → Jun 12, 2025 | — | |
| Plumbing | 2 sinks, 1 shower, 1 shower pan, 1 toilet, 1 water heater, 1 gas water heater, 1 gas heat. PP20241108934 | Nov 8, 2024 → Jul 7, 2025 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 1069, lot 056
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.