Converted · ground-floor conversion · Marina

3035 Baker St

Completed May 2023+3 units on this lot · now 1511 permits

The scope of work is to add 3 ADU's to level 1 per ordinance 162-16.

filed Aug 2020issued Nov 2021 · permit wait 1 year 3 monthscompleted May 2023 · built in 1 year 6 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$360,686 for 3 ADUs
one permit, 3 units; not a per-unit price
Permit wait
1 year 3 months
filed → issued
Build time
1 year 6 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitThe scope of work is to add 3 ADU's to level 1 per ordinance 162-16.
202008081395 · Doherty Restoration INC
filed Aug 2020 · issued Nov 2021 · done May 2023$321kcity record
RevisionRevision to 202008081395: adding an office to unit c, removing the court @ the notrth. Reducing the size of the sunken patio in rear yard. Change in mech system from ridiators to hini splits.
202111233078 · cites 202008081395 · Doherty Restoration INC
filed Nov 2021 · issued Jan 2022 · done May 2023—city record
SprinklersProvide fire sprinklers throughout ground floor incl new 2" (14 ft) underground fire service per nfpa 24. Total 53 heads. Ref 202008081395.
202206216648 · cites 202008081395 · O'Connor Plumbing & Fire Protection INC
filed Jun 2022 · issued Jun 2022 · done May 2023$35kcity record
RevisionAs-built for fire pa# 202110271248, install additional 1-wireless smoke detector in corridor & additional 6-wireless low freq sounders in 3 new adus #a, b, &c sleeping areas.
202303093326 · Aec Alarms
filed Mar 2023 · issued Mar 2023 · done May 2023$4,500city record
ElectricalUpgrade the existing fire alarm of 3-story 12 residential unit building to comply with 1103. 7. 6. 1.
EW202203212199
Mar 21, 2022 → May 8, 2023—
Electrical3 new ADU's on ground floor. 1 bed, 1 bath.
E20220610733
Jun 10, 2022 → May 4, 2023—
ElectricalTapping off main term, 25' tap rule, to feed 3x new adus via a lockable nema3r gutter. Ok to serve by pg&e. No service upgrade.
EW202301058175
Jan 5, 2023 → Jan 17, 2023—
PlumbingWork category: 2pb; two new ADU with two bathrooms, two kitchens and two laundry rooms. Two catch basins at back patio.
PW20220422830
Apr 22, 2022 → Nov 1, 2022—
PlumbingWork category: 1m; install 3 indoor fan coils heat pump and condenser units system.
PMW20220621518
Jun 21, 2022 → Nov 17, 2022—
PlumbingWork category: 4pb; provide fire sprinkler protection throughout ground floor. Provide new underground fire service.
PW20220626638
Jun 26, 2022 → May 8, 2023—
PlumbingWork category: 2pb; new ADU with one kitchen sink, one bathroom and one laundry.
PW20220627643
Jun 27, 2022 → Nov 1, 2022—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 0933, lot 005
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map