Converted · ground-floor conversion · Pacific Heights

3122 Sacramento St

Completed Apr 2025+2 units on this lot · now 811 permits

Construction of 2 adus in and existing formerly owner occupied storage space per 162-16, no change of occupancy or egress, required sprinklers to be under separate permit. Soft story under pa# 201708114650.

filed Sep 2020issued Jun 2022 · permit wait 1 year 9 monthscompleted Apr 2025 · built in 2 years 10 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$179,393 for 2 ADUs
one permit, 2 units; not a per-unit price
Permit wait
1 year 9 months
filed → issued
Build time
2 years 10 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitConstruction of 2 adus in and existing formerly owner occupied storage space per 162-16, no change of occupancy or egress, required sprinklers to be under separate permit. Soft story under pa# 201708114650.
202009083722 · Nora Carrasco Construction
filed Sep 2020 · issued Jun 2022 · done Apr 2025$145kcity record
Related permitUpgrade existing fire alarm system to comply with sffc section 1103. 7. 6. 1.
202403278765 · Crime Watch Security Sys Llc
filed Mar 2024 · issued Mar 2024 · done Jul 2024$34kcity record
RevisionRevision 202011068438- to correct location on fdc and corresponding water line.
202504164567 · Morris Todd Fire Protection INC
filed Apr 2025 · issued Apr 2025—city record
ElectricalElectrical survey for final inspection.
EW202302068833
Feb 6, 2023 → Feb 10, 2023—
ElectricalOnline electrical permit: 120 of buildings of 7-12 dwelling units. Modification of an existing fire alarm system by upgrading the fire panel, update all existing devices to be compatible with new facp and provide low frequency sounders in all sleeping areas to meet 75db.
E202312301510
Dec 30, 2023 → Jul 3, 2024—
PlumbingRenew pw20220420757: install main fire sprinkler line from street.
PP20240909833
Sep 9, 2024—
PlumbingRenew pp20191029755: adding drains to concrete slab floor & celing renovations as needed.
PP20240909835
Sep 9, 2024 → Dec 2, 2024—
PlumbingRenew pp20200708099: kitchen remodel. Replace sink & d/w in same locations.
PP20240909834
Sep 9, 2024 → Dec 2, 2024—
PlumbingRenew pw20220910762: work category: 11p; install main sprinkler service.
PP20240909832
Sep 9, 2024—
PlumbingWork category: 1m; final boiler inspection. This permit is a continuation of expired permit number: pmw20200917727.
PMW20241203509
Dec 3, 2024 → Dec 6, 2024—
PlumbingWork category: 11p; install main sprinkler service.
PW20250213074
Feb 13, 2025 → Mar 20, 2025—
3 other permits on this lot during the project, not counted
OtherTo obtain final inspection for work approved under pa# 2017-0811-4650 all work is complete.
202401164048
filed Jan 2024 · issued Jan 2024 · done Jan 2024—city record
OtherTo obtain final inspection for work approved under pa# 202007089779. 202009093755. All work is complete.
202403268622
filed Mar 2024 · issued Mar 2024 · done Apr 2025—city record
OtherTo obtain final inspection for work approved under pa# 201708084282. 202003036045. All work is complete.
202403268624
filed Mar 2024 · issued Mar 2024 · done Apr 2025—city record

These permits also cite 201708114650, 202007089779, 202009093755, 201708084282, 202003036045, 202011068438, which the city filed before our records begin.

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 1006, lot 011
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house