Converted · ground-floor conversion · Pacific Heights
3122 Sacramento St
Completed Apr 2025+2 units on this lot · now 811 permits
Construction of 2 adus in and existing formerly owner occupied storage space per 162-16, no change of occupancy or egress, required sprinklers to be under separate permit. Soft story under pa# 201708114650.
filed Sep 2020issued Jun 2022 · permit wait 1 year 9 monthscompleted Apr 2025 · built in 2 years 10 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$179,393 for 2 ADUs
one permit, 2 units; not a per-unit price
Permit wait
1 year 9 months
filed → issued
Build time
2 years 10 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Construction of 2 adus in and existing formerly owner occupied storage space per 162-16, no change of occupancy or egress, required sprinklers to be under separate permit. Soft story under pa# 201708114650. 202009083722 · Nora Carrasco Construction | filed Sep 2020 · issued Jun 2022 · done Apr 2025 | $145k | city record |
| Related permit | Upgrade existing fire alarm system to comply with sffc section 1103. 7. 6. 1. 202403278765 · Crime Watch Security Sys Llc | filed Mar 2024 · issued Mar 2024 · done Jul 2024 | $34k | city record |
| Revision | Revision 202011068438- to correct location on fdc and corresponding water line. 202504164567 · Morris Todd Fire Protection INC | filed Apr 2025 · issued Apr 2025 | — | city record |
| Electrical | Electrical survey for final inspection. EW202302068833 | Feb 6, 2023 → Feb 10, 2023 | — | |
| Electrical | Online electrical permit: 120 of buildings of 7-12 dwelling units. Modification of an existing fire alarm system by upgrading the fire panel, update all existing devices to be compatible with new facp and provide low frequency sounders in all sleeping areas to meet 75db. E202312301510 | Dec 30, 2023 → Jul 3, 2024 | — | |
| Plumbing | Renew pw20220420757: install main fire sprinkler line from street. PP20240909833 | Sep 9, 2024 | — | |
| Plumbing | Renew pp20191029755: adding drains to concrete slab floor & celing renovations as needed. PP20240909835 | Sep 9, 2024 → Dec 2, 2024 | — | |
| Plumbing | Renew pp20200708099: kitchen remodel. Replace sink & d/w in same locations. PP20240909834 | Sep 9, 2024 → Dec 2, 2024 | — | |
| Plumbing | Renew pw20220910762: work category: 11p; install main sprinkler service. PP20240909832 | Sep 9, 2024 | — | |
| Plumbing | Work category: 1m; final boiler inspection. This permit is a continuation of expired permit number: pmw20200917727. PMW20241203509 | Dec 3, 2024 → Dec 6, 2024 | — | |
| Plumbing | Work category: 11p; install main sprinkler service. PW20250213074 | Feb 13, 2025 → Mar 20, 2025 | — |
3 other permits on this lot during the project, not counted
| Other | To obtain final inspection for work approved under pa# 2017-0811-4650 all work is complete. 202401164048 | filed Jan 2024 · issued Jan 2024 · done Jan 2024 | — | city record |
| Other | To obtain final inspection for work approved under pa# 202007089779. 202009093755. All work is complete. 202403268622 | filed Mar 2024 · issued Mar 2024 · done Apr 2025 | — | city record |
| Other | To obtain final inspection for work approved under pa# 201708084282. 202003036045. All work is complete. 202403268624 | filed Mar 2024 · issued Mar 2024 · done Apr 2025 | — | city record |
These permits also cite 201708114650, 202007089779, 202009093755, 201708084282, 202003036045, 202011068438, which the city filed before our records begin.
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 1006, lot 011
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.