Converted · garage conversion · Mission
3225 24th St
Completed Nov 2022+2 units on this lot · now 68 permits
Priority processing - 100% affordable housing. Convert existing ground level garage space to create (2) new accessory dwelling units per ordinance 162-17, including foundation replacement and other necessary structural, mechanical, electrical and plumbing scope.
filed Jun 2020issued Jan 2022 · permit wait 1 year 7 monthscompleted Nov 2022 · built in 10 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$235,000 for 2 ADUs
one permit, 2 units; not a per-unit price
Permit wait
1 year 7 months
filed → issued
Build time
10 months
issued → completed
Builder
Evra Construction INCAlso on this project: A M West Mechanical INC, Crime Watch Security Sys Llc
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Priority processing - 100% affordable housing. Convert existing ground level garage space to create (2) new accessory dwelling units per ordinance 162-17, including foundation replacement and other necessary structural, mechanical, electrical and plumbing scope. 202006158748 · Evra Construction INC | filed Jun 2020 · issued Jan 2022 · done Nov 2022 | $210k | city record |
| Sprinklers | Install new overhead fire sprinkler system on ground level. Install new 2 " water service line included for fire sprinkler system. Ref. Permit 202006158748. 202202168056 · cites 202006158748 · A M West Mechanical INC | filed Feb 2022 · issued Feb 2022 · done Dec 2022 | $21k | city record |
| Sprinklers | Installation of new sprinkler monitoring system. Ref to 202202168056. 202206025471 · Crime Watch Security Sys Llc | filed Jun 2022 · issued Jun 2022 · done Nov 2022 | $4,000 | city record |
| Electrical | Electrical work for units remodeling. EW202204052544 | Apr 5, 2022 → Oct 7, 2022 | — | |
| Electrical | Upgrade residential unit from a 200a to 400a. E202207271578 | Jul 27, 2022 | — | |
| Electrical | Installation of a sprinkler monitoring system. EW202211037055 | Nov 3, 2022 → Nov 8, 2022 | — | |
| Plumbing | Work category: 2pb; addition of 2 bathrooms 2 kitchens 2 water heaters, relocate 4 wh, 2 new floor drains. PW20220228209 | Feb 28, 2022 → Aug 8, 2022 | — | |
| Plumbing | Work category: 4pa; install overhead fire sprinkler system in new ADU's. Install new water service line for new fire sprinkler system. PW20220322934 | Mar 22, 2022 → Nov 2, 2022 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 6518, lot 029
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.