Converted · ground-floor conversion · Portola

325A Bowdoin St

Completed Jun 2023+1 unit on this lot · now 24 permits

Add one unit on the 1st floor per ordinance 162-16 unit b. 1) add one kitchen and living room.

filed Sep 2020issued Sep 2021 · permit wait 1 year 1 monthcompleted Jun 2023 · built in 1 year 9 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$10,000
declared on the ADU permit
Permit wait
1 year 1 month
filed → issued
Build time
1 year 9 months
issued → completed
Builder
No contractor listed

Permits in this project

PermitWhatWhenDeclared
ADU permitAdd one unit on the 1st floor per ordinance 162-16 unit b. 1) add one kitchen and living room.
202009083707
filed Sep 2020 · issued Sep 2021 · done Jun 2023$10kcity record
ElectricalAddress correction for ew202002176713 & ew202012082117.
E20220606587
Jun 6, 2022 → Aug 19, 2022—
PlumbingWork category: 2pa; 3 bath room 1 kitchen.
PW20220803723
Aug 3, 2022 → Sep 7, 2022—
PlumbingWork category: 2pa; intall two new furnace.
PW20220803724
Aug 3, 2022 → Sep 7, 2022—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 5884, lot 026
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map