Converted · ground-floor conversion · Mission
3330 22nd St
Completed May 2024+1 unit on this lot · now 94 permits
Convert existing building manager's office to an ADU unit at the ground floor rear per the local ADU program.
filed Jun 2022issued Sep 2023 · permit wait 1 year 4 monthscompleted May 2024 · built in 7 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$20,500
declared on the ADU permit
Permit wait
1 year 4 months
filed → issued
Build time
7 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Convert existing building manager's office to an ADU unit at the ground floor rear per the local ADU program. 202206085888 · Hough Construction | filed Jun 2022 · issued Sep 2023 · done May 2024 | $21k | city record |
| Electrical | Install house panel by-pass. Separate building lights and appliances from the unit c. EW202404027742 | Apr 2, 2024 → Apr 8, 2024 | — | |
| Electrical | Run new circuit for unit in order to bring up to code. EW202404057825 | Apr 5, 2024 → Apr 10, 2024 | — | |
| Plumbing | Work category: 1p; modify gas line (separating gas line from house meter and new meter for unit #3332 c). PW20240305100 | Mar 5, 2024 → Mar 14, 2024 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 3617, lot 015
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.