Converted · garage conversion · Portola

3334 San Bruno Ave

Completed Jun 2026+3 units on this lot · now 128 permits

Add 3 adus in rear of 1st floor garage per ordinance 162-16, 162-17. Seismic retrofit compliance under pa # 202209233019. Sprinkler under separate permit: garage, basement & 1/f per fs-05, comply with nfpa 13 & nfpa 13r.

filed Jul 2021issued Mar 2025 · permit wait 3 years 9 monthscompleted Jun 2026 · built in 1 year 3 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$360,559 for 3 ADUs
one permit, 3 units; not a per-unit price
Permit wait
3 years 9 months
filed → issued
Build time
1 year 3 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAdd 3 adus in rear of 1st floor garage per ordinance 162-16, 162-17. Seismic retrofit compliance under pa # 202209233019. Sprinkler under separate permit: garage, basement & 1/f per fs-05, comply with nfpa 13 & nfpa 13r.
202107063800 · Genuine Construction INC
filed Jul 2021 · issued Mar 2025 · done Jun 2026$350kcity record
SprinklersModify existing fire sprinkler system for the new ADU and remodel ground and 1st floor total 17 heads. Ref pa# 2021-0706-3800.
202512242640 · cites 202107063800 · Magnum Construction Group INC
filed Dec 2025 · issued Dec 2025$11kcity record
ElectricalElectrical work for 3 new ADU units (units #10, 11, &12), the manager's office, the storage room, and the trash room in the garage. 400 amp service upgrade.
EW202508218891
Aug 21, 2025 → May 27, 2026—
ElectricalOnline electrical permit: 120 of buildings of 7-12 dwelling units. Upgrade existing fire alarm system to comply fire sprinkler monitoring with sffc 1103. 7. 6. .
E202601218385
Jan 21, 2026 → Jun 5, 2026—
PlumbingWork category: 2pb; plumbing work for new ADU units (#10, 11, &12) and laundry room.
PW20250821516
Aug 21, 2025 → May 27, 2026—
PlumbingWork category: 2m; install heat pumps and exhaust fans for 3 new ADU units, manager's office, laundry room, and trash room.
PMW20260114854
Jan 14, 2026 → May 27, 2026—
PlumbingWork category: 4pb; modify existing fire sprinkler system for the new ADU and remodel ground and 1st floor total 17 heads. Ref pa# 2021-0706-3800.
PW20260121021
Jan 21, 2026 → May 27, 2026—
PlumbingWork category: 2pa; kitchen and bath remodel for unit #1.
PW20260125114
Jan 25, 2026 → May 27, 2026—
2 other permits on this lot during the project, not counted
OtherApt 1: replace cabinets and plumbing fixture. No moving of walls or doors.
202511260537 · Genuine Construction INC
filed Nov 2025 · issued Nov 2025 · done Jun 2026$40kcity record
OtherRe-roofing (with torch).
202603026795 · A L P Roofing Corp
filed Mar 2026 · issued Mar 2026 · done Apr 2026$13kcity record

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 6172, lot 024
Why we call it an ADU
SF DBI flagged the permit as an ADU.