Converted · ground-floor conversion · Inner Richmond

338A 5th Ave

Completed Sep 2025+1 unit on this lot · now 39 permits

A. D. U. On 1st floor per ordinance 162-16 include relocate two 3-fixture full bathrooms, add one kitchen, office, bedroom, and living/dining area.

filed Nov 2021issued Apr 2023 · permit wait 1 year 5 monthscompleted Sep 2025 · built in 2 years 4 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$162,000
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
1 year 5 months
filed → issued
Build time
2 years 4 months
issued → completed
Builder
No contractor listed

Permits in this project

PermitWhatWhenDeclared
ADU permitA. D. U. On 1st floor per ordinance 162-16 include relocate two 3-fixture full bathrooms, add one kitchen, office, bedroom, and living/dining area.
202111192842
filed Nov 2021 · issued Apr 2023 · done Sep 2025$150kcity record
Sprinklers- install a voluntary fa system sprinkler monitoring per nfpa 72-2022 section 23. 8. 5. 5. 1 with 1 fire alarm control unit, wireless communicator mext to facu 1 mannual pull station, 1 smoke det. 11 low frequency horns at all residential sleeping area with refence sprinkler per nfpa 13.
202409181048 · Poly - On Electrical
filed Sep 2024 · issued Sep 2024 · done May 2025$12kcity record
Related permitTo obtain a final inspection for work approved under prevous permit 202310199024.
202503112028 · Best Care Fire Protection
filed Mar 2025 · issued Mar 2025 · done May 2025—city record
ElectricalInstall 200 amps service with 3 meters.
EW202311175262
Nov 17, 2023 → Dec 30, 2024—
ElectricalNew rewiring unit apt c, 2 bedrooms, 2 bathroom, laundry room and kitchen area. Subpanel unit c.
EW202311175263
Nov 17, 2023 → Dec 30, 2024—
ElectricalUpgrade 200 amps electrical service.
EW202406119253
Jun 11, 2024 → Dec 27, 2024—
ElectricalInstall a dedicated functin fa system sprinkler monitor per nfpa 72-2022 section 23. 8. 5. 5. 1 with reference sprinkler permit nfpa13 pa#: 202310199024.
E202409186955
Sep 18, 2024 → May 20, 2025—
PlumbingWork category: 4pa; install an nfpa 13 fire sprinkler system for the entire first floor, including a 2" fire service. The previous plumbing permit #pp20231024699 and building permit #202310199024 expired/were suspended. Obtain a new plumbing permit for final inspection. New building permit #202503112028.
PW20250318834
Mar 18, 2025 → Apr 22, 2025—
PlumbingWork category: 2pa; to obtain a final inspection for work approved under previous permit # pw20230823633.
PW20250623117
Jun 23, 2025 → Jun 30, 2025—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 1436, lot 033
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map