Converted · ground-floor conversion · Hayes Valley
345 Fulton St
In progress+3 units on this lot · now 311 permit
Addition of three ADU units at the ground floor per the local ADU program for a total of 31 units. Modification of sprinklers at work area as required and under a separate permit; entire ground floor assembly to be upgraded to a 1-hour assembly per information sheet fs-05.
filed May 2022issued Oct 2023 · permit wait 1 year 5 months3 years 1 month since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$589,020 for 3 ADUs
one permit, 3 units; not a per-unit price
Permit wait
1 year 5 months
filed → issued
Build time
in progress
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Addition of three ADU units at the ground floor per the local ADU program for a total of 31 units. Modification of sprinklers at work area as required and under a separate permit; entire ground floor assembly to be upgraded to a 1-hour assembly per information sheet fs-05. 202205114051 · S L M Development INC | filed May 2022 · issued Oct 2023 | $589k | city record |
1 other permit on this lot during the project, not counted
| Other | Unit 50: plaster repairs on ceiling of living room. 202511240271 · Redlog Construction Group | filed Nov 2025 · issued Nov 2025 · done Dec 2025 | $5,000 | city record |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 0792, lot 007A
- Why we call it an ADU