Converted · ground-floor conversion · Marina
3515 Fillmore St
In progress+2 units on this lot · now 232 permits
Remodel ground floor at rear of garage to create two new ADU's per ordiance 162-6 add access hallway from main entry & new posts/bm at garage parking areas. Unit a is 495 SF. Unit b is 700 SF. Unit a is formed from the existing space at the lower level of current unit #107. **maher n/a**.
filed Sep 2020issued Nov 2023 · permit wait 3 years 2 months3 years since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$394,000 for 2 ADUs + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
3 years 2 months
filed → issued
Build time
in progress
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Remodel ground floor at rear of garage to create two new ADU's per ordiance 162-6 add access hallway from main entry & new posts/bm at garage parking areas. Unit a is 495 SF. Unit b is 700 SF. Unit a is formed from the existing space at the lower level of current unit #107. **maher n/a**. 202009093733 · North Point Construction INC | filed Sep 2020 · issued Nov 2023 | $345k | city record |
| Related permit | Upgrade existing fire alarm system to comply with sffc section 1103. 7. 6. 1 to meet 75db in all sleeping areas. Ref ADU permit 202009093733. 202602065413 · cites 202009093733 · San Francisco Fire Protection | filed Feb 2026 · issued Feb 2026 | $49k | city record |
1 other permit on this lot during the project, not counted
| Other | Revision to 202209093733: change to ground floor plan to included new half bath with sink & toilet in common area garage. Unit a & b layout change. 202404119775 · North Point Construction INC | filed Apr 2024 · issued May 2024 | $10k | city record |
These permits also cite 202209093733, which the city filed before our records begin.
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 0467A, lot 014
- Why we call it an ADU
- Two independent model reviewers agreed the permit creates an ADU: “"remodel ground fl at rear of garage to create two new adu's per ordiance 162-6 ... unit a is 495 sf. unit b is 700 sf."; units 21 → 23”