Converted · ground-floor conversion · Oceanview/Merced/Ingleside
37 Sadowa St
Completed Aug 2026+1 unit on this lot · now 25 permits
Add 1 new dwelling (ADU) at ground floor with 2 bedrooms, 2 baths, 1 kitchen, 1 family per local code 95-17.
filed Oct 2024issued Jul 2025 · permit wait 9 monthscompleted Aug 2026 · built in 1 year 1 month
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$211,000
declared on the ADU permit
Permit wait
9 months
filed → issued
Build time
1 year 1 month
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Add 1 new dwelling (ADU) at ground floor with 2 bedrooms, 2 baths, 1 kitchen, 1 family per local code 95-17. 202410173137 · Zhang General Construction | filed Oct 2024 · issued Jul 2025 · done Aug 2026 | $211k | city record |
| Electrical | Ref to ADU pa# 202410173137: 2 baths, 1 kitchen, 1 laundry, 22 lights, 22 receptacles, 20 switches, water heater, 100 amp sub panel, 3 smoke detectors. E202508214960 | Aug 21, 2025 → Mar 4, 2026 | — | |
| Electrical | To continue for permit#e202405294661, 2/f: relocate existing kitchen and remodel existing bath. Add(1) new bath and infill lightwell. E202508224996 | Aug 22, 2025 → Mar 11, 2026 | — | |
| Plumbing | 2 bathrooms, 1 shower pan, 1 kitchen, washer/dryer, water heater, with underground for ADU. PP20250821272 | Aug 21, 2025 → Mar 3, 2026 | — | |
| Plumbing | Continue pp#20240529076. Remodel 1 kitchen & 2 bathrooms, 1 laundry with 1 shower pan. PP20250822302 | Aug 22, 2025 → Nov 19, 2025 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 7139, lot 008
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.