Converted · legalization · Outer Mission

399A Ellington Ave

Completed Nov 2023+1 unit on this lot · now 24 permits

Fire retardant wall between units. May need to alter electrical and plumbing if necessary for legalization of extg unit. Legalization per ordinance 43-14 to comply with complaints #201931514 and 201931071.

filed Oct 2019issued Sep 2023 · permit wait 3 years 11 monthscompleted Nov 2023 · built in 55 days
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$29,500
declared on the ADU permit
Permit wait
3 years 11 months
filed → issued
Build time
55 days
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitFire retardant wall between units. May need to alter electrical and plumbing if necessary for legalization of extg unit. Legalization per ordinance 43-14 to comply with complaints #201931514 and 201931071.
201910285792 · J P E Construction
filed Oct 2019 · issued Sep 2023 · done Nov 2023$30kcity record
ElectricalKitchen outlets, bathroom outlets.
E202310039862
Oct 3, 2023 → Nov 2, 2023—
Plumbing1 new wall gas heater in living room.
PM20231003301
Oct 3, 2023 → Oct 26, 2023—
PlumbingInstall kitchen sink and faucet. Bathroom sink and faucet.
PP20231003302
Oct 3, 2023 → Oct 26, 2023—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 7066, lot 013A
Why we call it an ADU
Two independent model reviewers agreed the permit creates an ADU: “"legalization of extg unit. legalization per ordinance 43-14"; units 1 → 2; use 1 family dwelling → 2 family dwelling”