In progress+1 unit on this lot · now 25 permits

Rear horizontal additon @ basement & 1st floor kitchen. New coat closert & powder rm. Inexisting dining room. Newmaster bath on part of existing 2nd floor open deck replace existing gas gravity furnace & dosmestic hot water with heat pump. New ADU @ 1st floor.

filed Dec 2019issued Nov 2024 · permit wait 4 years 10 months2 years since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$520,000 + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
4 years 10 months
filed → issued
Build time
in progress
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitRear horizontal additon @ basement & 1st floor kitchen. New coat closert & powder rm. Inexisting dining room. Newmaster bath on part of existing 2nd floor open deck replace existing gas gravity furnace & dosmestic hot water with heat pump. New ADU @ 1st floor.
201912311084 · K L W Construction INC
filed Dec 2019 · issued Nov 2024$500kcity record
RevisionStructural revision 201912311084- provide new interior conc footing per fied inspection change condition at site no existing footing. Provide new conc retaining wall at rear yard.
202504224960 · cites 201912311084 · K L W Construction INC
filed Apr 2025 · issued May 2025$20kcity record
Electrical4006 & 4006a 25th st. Build rear addition & basement. Upgrade existing electrical panel to 200 amp panel.
E202501279581
Jan 27, 2025—
PlumbingBuild horizontal addition at basement. 1st floor kitchen & bathroom remodel. Underground sewer lines. Gas heater.
PP20250127177
Jan 27, 2025—
PlumbingTo renew #pmw20260724836: work category: 1m; install new radiant floor heating system for basement and first floor area. Install tankless water heater in the garage area with pvc flue pipe terminated to the front of the building. Connect heating system to the water heater. Install three zone ductless mini split system for second floor area. Install outdoor condenser on the roof.
PM20260724424
Jul 24, 2026 → Aug 7, 2026—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 6537, lot 006
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house