Converted · interior conversion · Inner Richmond

4215 Geary Blvd

Completed Oct 2023+1 unit on this lot · now 18 permits

Convert existing office space to an ADU on second floor.

filed Dec 2019issued May 2022 · permit wait 2 years 5 monthscompleted Oct 2023 · built in 1 year 5 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$183,332
declared across 3 permits: the ADU permit plus its sub-permits
Permit wait
2 years 5 months
filed → issued
Build time
1 year 5 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitConvert existing office space to an ADU on second floor.
201912270837 · Liu Zhizhao Construction Company
filed Dec 2019 · issued May 2022 · done Oct 2023$160kcity record
SprinklersAdd sprinklers system at residential area according to improvement 201912270837 per nfpa 13 2016 (total: 31 new sprinklers).
202208049943 · cites 201912270837 · Project Contractor INC
filed Aug 2022 · issued Aug 2022 · done Oct 2023$19kcity record
SprinklersInstallation of a new sprinkler monitoring system. Ref permit 202208049943.
202308164575 · Crime Watch Security Sys Llc
filed Aug 2023 · issued Aug 2023 · done Oct 2023$4,732city record
ElectricalRemodel 2nd floor.
E202208081778
Aug 8, 2022 → Aug 25, 2023—
Electrical400 amp new service.
E202302225169
Feb 22, 2023 → Aug 25, 2023—
ElectricalInstallation of a sprinkler monitoring system.
EW202309083698
Sep 8, 2023 → Oct 5, 2023—
PlumbingRemodel the 2nd floor.
PP20220808378
Aug 8, 2022 → Aug 25, 2023—
PlumbingWork category: 4pa; add sprinklers system at residential area according to app# 2022 0804 9943 (also refer to building improvement app#2019 1227 0837) per nfpa 13 2016 (total: 31 new sprinkler heads).
PW20220920018
Sep 20, 2022 → Sep 18, 2023—
2 other permits on this lot during the project, not counted
OtherRev to pa201912270837: minor change of bathroom layout & change to heating system. Add electrical panels at lobby. Replace existing metal door with metal gate. Upgrade roof framing under new deck.
202207077917 · Liu Zhizhao Construction Company
filed Jul 2022 · issued Aug 2022 · done Oct 2023$18kcity record
OtherReroofing. Full tear off of old and replace with 20 bigs ply fresco, 5 bigs silicone overlay.
202301109971 · Lifetime Roofing Renovation
filed Jan 2023 · issued Jan 2023 · done Feb 2023$12kcity record

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 1538, lot 037
Why we call it an ADU
Two independent model reviewers agreed the permit creates an ADU: “"convert existing office space to an adu on second floor." Existing units: 0 → Proposed units: 1; office → 1 family dwelling”
Claim this project or house

City record of the ADU permitProperty Information Map