Converted · garage conversion · Lone Mountain/USF

43 Cole St

Completed Jul 2023+2 units on this lot · now 910 permits

ADU (unit a&b) per ord 162-16 on 1st flr per plans. Unit a eliminated existing garage to create a bedroom, kitchen, living/offic & full bath. Unit b: convert existing storage & mech rm into a bedroom, kitchen/living & full bath.

filed Nov 2019issued Sep 2021 · permit wait 1 year 10 monthscompleted Jul 2023 · built in 1 year 10 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$187,347 for 2 ADUs
one permit, 2 units; not a per-unit price
Permit wait
1 year 10 months
filed → issued
Build time
1 year 10 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitADU (unit a&b) per ord 162-16 on 1st flr per plans. Unit a eliminated existing garage to create a bedroom, kitchen, living/offic & full bath. Unit b: convert existing storage & mech rm into a bedroom, kitchen/living & full bath.
201911046394 · W F Construction Co
filed Nov 2019 · issued Sep 2021 · done Jul 2023$120kcity record
SprinklersInstall new fire sprinkler system per nfpa 13 for the ground floor ADU only. Included 2" underground fire service. Total = 23 heads.
202206075777 · Magnum Construction Group INC
filed Jun 2022 · issued Jul 2022 · done Mar 2023$18kcity record
SprinklersAs built fire sprinkler system plan. Ref pa#202206075777.
202208291491 · Magnum Construction Group INC
filed Aug 2022 · issued Sep 2022—city record
AddressUpgrade existing fire alarm system, with 1-addressible fire alarm unit, 1-wireless communicator next to facu, 6-addressible smoke detectors, 1-addressible heat detectors, 5-addressible manual pull stations, 3-horn/strobes, 26-low freq horns @ all sleeping areas, 1-addressible control module, 2-addressible monitors.
202302272628 · Poly - On Electrical
filed Feb 2023 · issued Feb 2023 · done Mar 2023$40kcity record
RevisionRevision to pa 2019-1104-6394 unit a reconfigure the layout of kitchen, living room, bedroom; riase the 1st floor and create a new staircase; unit b relocate the closet and kitchen; details no change. Shall follow previous approved drawings unless otherwise noted.
202304256401 · cites 201911046394
filed Apr 2023 · issued Jun 2023 · done Jul 2023$10kcity record
ElectricalNew electrical work to eliminated garage to create a bedroom, a kitchen, a living/office & a full bath in unit a per plan; in unit b convert existing storage & mechanical room into a bedroom, a kitchen/living & a full bath per plan. This permit will cover unit a & b may be included 1 sub-panel.
EW202109198467
Sep 19, 2021 → Feb 25, 2022—
ElectricalUnit b convert storage & mechanical room into bedroom, a kitchen /living and a full bath per plan.
EW202112150306
Dec 15, 2021 → Feb 25, 2022—
ElectricalUpgrade existing fire alarm system, with 1-addressible fire alarm unit, 1-wireless communicator next to facu, 6-addressible smoke detectors, 1-addressible heat detectors, 5-addressible manual pull stations, 3-horn/strobes, 26-low freq horns @ all sleeping areas, 1-addressible control module, 2-addressible monitors. Upgrade the existing fire alarm to comply with sffc sec 1103. 7. 6. 1.
E202302275232
Feb 27, 2023 → Mar 10, 2023—
PlumbingWork category: 3pa; ground floor new ADU unit a & b new kitchen and full bath in each unit with shower pan including under ground work.
PW20210919862
Sep 19, 2021 → Mar 2, 2022—
PlumbingWork category: 4pa; install new fire sprinkler system per nfpa 13 for the ground floor only. Included 2" underground fire service. . Total= 23 heads.
PW20220726460
Jul 26, 2022 → Mar 10, 2023—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 1190, lot 001A
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map