Detached · Sunset/Parkside

4309 Kirkham St

Completed Jun 2023+1 unit on this lot5 permits

Addition of one detached, hcd approved and inspected, factory-built ADU unit in the rear yard per the state ADU program. Unit will be installed on concrete t-footing foundation connected to site utilities.

filed Jun 2022issued Mar 2023 · permit wait 9 monthscompleted Jun 2023 · built in 3 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$136,607
declared on the ADU permit
Permit wait
9 months
filed → issued
Build time
3 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAddition of one detached, hcd approved and inspected, factory-built ADU unit in the rear yard per the state ADU program. Unit will be installed on concrete t-footing foundation connected to site utilities.
202206307496 · Abodu Inc
filed Jun 2022 · issued Mar 2023 · done Jun 2023$137kcity record
ElectricalUpgrade exisitng panel to 200 amps. Connect ADU to existing panel.
E202304066000
Apr 6, 2023 → Jun 20, 2023—
Electrical1. 7kw roof mounted photovoltaic solar system flush mounted - 4 roof-mounted solar pv modules, 425 watts per module, 4 interactive inverter, total no. Of rating 1. 536 kw.
EW202304270716
Apr 27, 2023 → Jun 1, 2023—
PlumbingConnect detached ADU sewer to existing main home sewer lateral.
PP20230406341
Apr 6, 2023 → Jun 15, 2023—
PlumbingHvac condesor unit installation on exterior of detached ADU. Interior mini-split system and rough plumbing were install at the ractor and were insepcted and approved by cal dhcd, div of codes and standards.
PM20230602274
Jun 2, 2023 → Jun 15, 2023—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 1893, lot 045
Why we call it an ADU
SF DBI flagged the permit as an ADU.