Converted · ground-floor conversion · Outer Richmond

475A 18th Ave

Completed Sep 2025+1 unit on this lot · now 311 permits

Add a 2 bedrooms ADU on the ground floor. And interior remodel of the exsiting two units under a separate permit.

filed Apr 2023issued Feb 2024 · permit wait 10 monthscompleted Sep 2025 · built in 1 year 7 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$300,000
declared on the ADU permit
Permit wait
10 months
filed → issued
Build time
1 year 7 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAdd a 2 bedrooms ADU on the ground floor. And interior remodel of the exsiting two units under a separate permit.
202304246350 · H & Bo Construction INC
filed Apr 2023 · issued Feb 2024 · done Sep 2025$300kcity record
ADU permitRevision to ADU 202304246350- to remove notes fire sprinkler on the site plan. Fire sprinkler not required for this project and revised ADU floor plan. Proposed occupancy changed from r-2 to r-3.
202409251560 · H & Bo Construction INC
filed Sep 2024 · issued Sep 2024 · done Sep 2025—city record
Related permitInterior remodel of existing two units on this permit (475-477 18th ave). ADU under separate permit app #202304246350. ***no structural work under this permit***.
202307061618 · cites 202304246350 · H & Bo Construction INC
filed Jul 2023 · issued Sep 2024 · done Sep 2025$486kcity record
RevisionRevision to 202304246350. Updating structural plans to match architectural blue beam approved plans.
202403127628 · cites 202304246350 · H & Bo Construction INC
filed Mar 2024 · issued Mar 2024 · done Sep 2025—city record
ElectricalUf ground. Add 60 amp subpanel. Add one kitchen in ADU and new 40 gallon heat pump. 40 lights, 20 switch, 1 fan, 1 dishwasher, 1 g. D. , 1 microwave, 1 ranges, 5 smoke detectors.
E202404243942
Apr 24, 2024 → Jul 1, 2025—
Electrical475-477 18th ave: upgrade electrical main service to 400 amp at existing location. Install 125 amp subpanel at each units. Top floor install 80 amp subpanel. 475a 18th ave: install 125amp to ADU.
E202409207003
Sep 20, 2024 → May 29, 2025—
ElectricalInstall switches and outlets in entire unit.
E202409207012
Sep 20, 2024 → Jul 1, 2025—
ElectricalFor address 477 18th ave: switches and outlets in entire unit. Install ev chareger at garagae. Install 80amp panel to top floor.
E202409207013
Sep 20, 2024 → Jul 1, 2025—
PlumbingAdd one bath and one kitchen in ADU and new underground. One shower pan.
PP20240424496
Apr 24, 2024 → Jul 1, 2025—
Plumbing475-477 18th ave: upgrade 1 kitchen and 2 bathroom. 2 shower pans, 2 laundry with sink each unit. New tankless. Upgrade 1' water line to garagae. Upgrade gas line.
PP20240920069
Sep 20, 2024 → Jul 11, 2025—
Plumbing475-477 18th ave: install 2 furnaces at existing location. 475a 18th ave: install new mini split system at ADU.
PM20240920070
Sep 20, 2024 → Jul 1, 2025—
1 other permit on this lot during the project, not counted
OtherRev 202307061618- to remove side windows and change the size of rear window in the sunroom, extend laundry room and add a laundry sink and adding a electric fireplace on the 2nd and 3rd floor units.
202409251558 · H & Bo Construction INC
filed Sep 2024 · issued Sep 2024 · done Jul 2025—city record

Trade permits show what work was done and when; the city does not record who pulled them.