Converted · garage conversion · Mission

484 Guerrero St

Completed Jan 2026+2 units on this lot · now 89 permits

Renovate 1 guest room at ground floor, install full kitchen & reconfigure for 1-bedroom layout to become ADU. Convert 1-car garage into 1 ADU (state program). ADU to be a studio apartment. Modifications to existing sprinklers under separate permit. Upgrade fire alarm under separate permit.

filed Dec 2022issued Feb 2024 · permit wait 1 year 2 monthscompleted Jan 2026 · built in 2 years
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$228,522 for 2 ADUs
one permit, 2 units; not a per-unit price
Permit wait
1 year 2 months
filed → issued
Build time
2 years
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitRenovate 1 guest room at ground floor, install full kitchen & reconfigure for 1-bedroom layout to become ADU. Convert 1-car garage into 1 ADU (state program). ADU to be a studio apartment. Modifications to existing sprinklers under separate permit. Upgrade fire alarm under separate permit.
202212228969 · Doherty Restoration INC
filed Dec 2022 · issued Feb 2024 · done Jan 2026$200kcity record
SprinklersProvide fire sprinkler throughout ground floor only and new underground per nfpa 24. Ref pa# 202212228969.
202412277453 · cites 202212228969 · O'Connor Plumbing & Fire Protection INC
filed Dec 2024 · issued Dec 2024 · done Jul 2025$24kcity record
RevisionAs-built: corrected ground floor layout an d added several new devices on the ground floor. Ref pa #202303093327.
202506128624 · Crime Watch Security Sys Llc
filed Jun 2025 · issued Jun 2025 · done Jun 2025$4,224city record
RevisionRevision to 202212228969: revise wall layout in 1st/f.
202510036732 · cites 202212228969 · Doherty Restoration INC
filed Oct 2025 · issued Dec 2025 · done Jan 2026—city record
ElectricalOnline electrical permit: 60 of buildings of 6 dwelling units or less. Modification of an existing fire alarm system by upgrading the fire panel, update all existing devices to be compatible with new facp and provide low frequency sounders in all sleeping areas to meet.
E202404093640
Apr 9, 2024 → Jun 20, 2025—
ElectricalInstallation of new wiring for back unit on ground level and also installation of wiring for ADU on ground level.
EW202501073318
Jan 7, 2025 → Jun 12, 2025—
PlumbingWork category: 2pb; two ADU additions with two kitchens and two bathroom.
PW20241025686
Oct 25, 2024 → Jun 20, 2025—
PlumbingWork category: 4pb; provide fire sprinkler coverage throughout ground floor per nfpa 13, and new underground per nfpa 24.
PW20250106095
Jan 6, 2025 → Jun 20, 2025—
PlumbingWork category: 1m; install two heat pump system one for front uni and for back unit.
PMW20250115357
Jan 15, 2025 → Jun 12, 2025—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 3567, lot 009
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map