Detached · Portola
488 Hamilton St
Completed Mar 2023+1 unit on this lot3 permits
New 507 SF hud/hcd approved manufactured unit to be installed on permanent foundation as a detached ADU.
filed May 2021issued Apr 2022 · permit wait 11 monthscompleted Mar 2023 · built in 11 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$91,908
declared on the ADU permit
Permit wait
11 months
filed → issued
Build time
11 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | New 507 SF hud/hcd approved manufactured unit to be installed on permanent foundation as a detached ADU. 202105039714 · Villa Technologies INC | filed May 2021 · issued Apr 2022 · done Mar 2023 | $92k | city record |
| Electrical | Service upgrade to 400 amps and underground sub feed to ADU. EW202206144088 | Jun 14, 2022 → Feb 9, 2023 | — | |
| Plumbing | Detatached ADU: new drain & water hookup. PP20220621522 | Jun 21, 2022 → Mar 2, 2023 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 6042, lot 038
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.