Converted · legalization · Inner Richmond

4908 California St

Completed Apr 2025+1 unit on this lot · now 310 permits

Legalization of ground flr studio unit per ord# 43-14. Sprinkler and fire alarm system as required to be pulled under separate permit.

filed Oct 2019issued Dec 2022 · permit wait 3 years 1 monthcompleted Apr 2025 · built in 2 years 4 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$77,000
declared across 3 permits: the ADU permit plus its sub-permits
Permit wait
3 years 1 month
filed → issued
Build time
2 years 4 months
issued → completed
Builder
No contractor listed

Permits in this project

PermitWhatWhenDeclared
ADU permitLegalization of ground flr studio unit per ord# 43-14. Sprinkler and fire alarm system as required to be pulled under separate permit.
201910285769
filed Oct 2019 · issued Dec 2022 · done Apr 2025$46kcity record
Related permitInstallation of fire sprinlker for ground floor and ADU only. Ref 201910285769 24 heads.
202305087338 · cites 201910285769 · Chung Wah Plumbing & Fire Protection
filed May 2023 · issued Apr 2024 · done Nov 2024$24kcity record
Related permitUpgrade existing fire alarm system. To comply with sffc 1103. 7. 6. 1.
202409050167 · Crime Watch Security Sys Llc
filed Sep 2024 · issued Sep 2024 · done Oct 2024$7,000city record
ElectricalRelocate existing 300amp electrical service. Provide 4 meters ( 3-units / 1-hi=ouse).
EW202307172541
Jul 17, 2023 → Oct 17, 2023—
ElectricalOnline electrical permit: 60 of buildings of 6 dwelling units or less. Modification of an existing fire alarm system by upgrading the fire panel, update all existing devices to be compatible with new facp and provide low frequency sounders in all sleeping areas to meet.
E202409146896
Sep 14, 2024 → Oct 25, 2024—
ElectricalGarage lighting and receptalce. Ref to inspection report cc-8355. 2 circuits, #12/2 feeder, 12 lights, 4 switches, 5 receptacles.
E20250218095
Feb 18, 2025 → Apr 18, 2025—
ElectricalThe house has a back unit addressed as 4906-a and partial unit circuitry needed to be rewired per code. Replace power outlets, retrofit lighting fixtures to led. Add separate circuits for the bathroom lighting and power outlet. All new receptacles are changed to tamper resistant.
EW202504145607
Apr 14, 2025 → Apr 18, 2025—
PlumbingWork category: 4pa; fire sprinkler installed for the ground floor.
PW20240311224
Mar 11, 2024 → May 1, 2025—
PlumbingWork category: 4pa; install fire sprinkler system for ground floor only.
PW20240402751
Apr 2, 2024 → Aug 23, 2024—
PlumbingWork category: 1p; 3r report: application cc-8355. Plumbing corrections.
PW20240906386
Sep 6, 2024 → Dec 9, 2024—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 1371, lot 019
Why we call it an ADU
Two independent model reviewers agreed the permit creates an ADU: “"legalization of ground flr studio unit per ord# 43-14"; Existing units: 2 → Proposed units: 3”
Claim this project or house

City record of the ADU permitProperty Information Map