Converted · interior conversion · Presidio Heights

55 Lupine Ave

Completed Jan 2024+1 unit on this lot · now 37 permits

Per ADU ordinance# 162-16, add 1 new studio unit on existing conditional space.

filed Jan 2020issued Oct 2022 · permit wait 2 years 9 monthscompleted Jan 2024 · built in 1 year 2 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$50,331
declared across 3 permits: the ADU permit plus its sub-permits
Permit wait
2 years 9 months
filed → issued
Build time
1 year 2 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitPer ADU ordinance# 162-16, add 1 new studio unit on existing conditional space.
202001303166 · All Bay Cities Construction
filed Jan 2020 · issued Oct 2022 · done Jan 2024$27kcity record
SprinklersInstallation of 13 fire sprinkler at ground floor dwelling and relevance egress according to pa#: 202001303166 per nfpa13 2022 and underground piping per nfpa 24 (trench, backfill and sidewalk repair by separate permit).
202304135646 · cites 202001303166 · Project Contractor INC
filed Apr 2023 · issued Apr 2023 · done Jan 2024$15kcity record
SprinklersInstallation of a new sprinkler monitoring system.
202311271390 · Crime Watch Security Sys Llc
filed Nov 2023 · issued Nov 2023 · done Jan 2024$8,656city record
ElectricalNew accessory dwelling unit on existing conditional space, new kitchen, new bathrom and dining room.
E202211303821
Nov 30, 2022 → Dec 26, 2023—
ElectricalOnline electrical permit: 60 of buildings of 6 dwelling units or less. Installation of a sprinkler monitoring system.
E202312071062
Dec 7, 2023 → Dec 29, 2023—
PlumbingNew accessory dwelling unit on existing conditional space, new kitchen, new bathrom and shower pan.
PP20221130359
Nov 30, 2022 → Jan 2, 2024—
PlumbingWork category: 4pa; installation of (13) fire sprinkler at ground floor dwelling & relevance egress according to fire sprinkler permit app# 2023 0413 5646, also refer to building permit app# 2020 0130 3166 per nfpa 13 2022 & underground piping per nfpa 24 (trench, backfill & sidewalk repair by separate permit).
PW20230417281
Apr 17, 2023 → Dec 1, 2023—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 1057, lot 020
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map