Converted · interior conversion · West of Twin Peaks
579A Miramar Ave
Completed Mar 2024+1 unit on this lot · now 23 permits
Addition of a streamlined ADU within an existing single-family dwelling. The project consists of updating electrical and plumbing to code and upgrading some walls and entry doors to comply with fire code. It also involves renovation of the cooking area and bathrooms. State ADU per govt code sec 65852. 2.
filed Nov 2020issued May 2023 · permit wait 2 years 6 monthscompleted Mar 2024 · built in 10 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$92,409
declared on the ADU permit
Permit wait
2 years 6 months
filed → issued
Build time
10 months
issued → completed
Builder
No contractor listed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Addition of a streamlined ADU within an existing single-family dwelling. The project consists of updating electrical and plumbing to code and upgrading some walls and entry doors to comply with fire code. It also involves renovation of the cooking area and bathrooms. State ADU per govt code sec 65852. 2. 202011189234 | filed Nov 2020 · issued May 2023 · done Mar 2024 | $92k | city record |
| Electrical | I am installing 1 subpanel-612 afci breakers-rewire kitchen only refrigerator, garbage disposal, dishwasher, and 2 switch points. EW202305251410 | May 25, 2023 → Jan 31, 2024 | — | |
| Plumbing | Provide plumbing rough and finish for new basement- ADU buildout per pa# 202011189234: nov 201954683: new kitchen and new laundry only. PP20230829717 | Aug 29, 2023 → Jan 19, 2024 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 3175, lot 003
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.