Converted · interior conversion · Mission

61 Cypress St

In progress+1 unit on this lot · now 11 permit

Building 2: exterior materials repair & replacement, & interior renovation of cypress facing structure(structure 2). Includes structural upgrades, framing repairs. New slab on grade & replacement of perimeter footings. Move existing floor framing down 24"± to accommodate for new ADU at level above garage. . .

filed Jan 2026issued Mar 2026 · permit wait 2 months7 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$222,120 + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
2 months
filed → issued
Build time
in progress
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitBuilding 2: exterior materials repair & replacement, & interior renovation of cypress facing structure(structure 2). Includes structural upgrades, framing repairs. New slab on grade & replacement of perimeter footings. Move existing floor framing down 24"± to accommodate for new ADU at level above garage. . .
202512292863 · Bradford Construction INC
filed Jan 2026 · issued Mar 2026$222kcity record

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 6518, lot 008
Why we call it an ADU
Two independent model reviewers agreed the permit creates an ADU: “"move (e) floor framing down 24"± to accommodate for new adu at level above garage"; Existing units: 0 → Proposed units: 1; use prkng garage/private → 1 family dwelling”
Claim this project or house

City record of the ADU permitProperty Information Map