Converted · ground-floor conversion · Excelsior

644 Russia Ave

In progress+1 unit on this lot · now 31 permit

Addition of one ADU unit at the first floor under the state ADU program.

filed Apr 2022issued Aug 2022 · permit wait 5 months4 years 2 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$86,000
declared on the ADU permit
Permit wait
5 months
filed → issued
Build time
in progress
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAddition of one ADU unit at the first floor under the state ADU program.
202204051546 · Goodman Construction & Design Co INC
filed Apr 2022 · issued Aug 2022$86kcity record

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 6278, lot 001
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map

Converted · ground-floor conversion ADU at 644 Russia Ave · MiCasa