Converted · legalization · Hayes Valley

65 Laussat St

Completed Sep 2024+1 unit on this lot · now 34 permits

Legalize the as-built basement area into an accessory dwelling unit (ADU) per gov't code 65852. 2 - and asssign #67a as the proposed ADU's address.

filed Sep 2022issued Aug 2023 · permit wait 11 monthscompleted Sep 2024 · built in 1 year 1 month
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$148,000
declared on the ADU permit
Permit wait
11 months
filed → issued
Build time
1 year 1 month
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitLegalize the as-built basement area into an accessory dwelling unit (ADU) per gov't code 65852. 2 - and asssign #67a as the proposed ADU's address.
202209283272 · Prosper Construction Development INC
filed Sep 2022 · issued Aug 2023 · done Sep 2024$148kcity record
ElectricalRef to building pa# 202209283272: main service for electrical running dedicated circuite & installing a sub panel.
E202402122360
Feb 12, 2024—
PlumbingNeed to add to the permit number pp20240212292. A kitchen sink and with d installation.
PP20240228531
Feb 28, 2024 → Jul 8, 2024—
Plumbing3 mini splits.
PM20240305632
Mar 5, 2024 → Mar 8, 2024—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 0858, lot 013A
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map