Converted · legalization · Excelsior
68 Vienna St
Completed Dec 2025+1 unit on this lot · now 25 permits
ADU legalization at ground flr. Comply with n. O. V 202174122. Replace door with a fire door, make bigger landing at entrance between foyer and garage, bring existing kitchen to code, bring existing media room to code.
filed May 2021issued Sep 2024 · permit wait 3 years 4 monthscompleted Dec 2025 · built in 1 year 2 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$185,000
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
3 years 4 months
filed → issued
Build time
1 year 2 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | ADU legalization at ground flr. Comply with n. O. V 202174122. Replace door with a fire door, make bigger landing at entrance between foyer and garage, bring existing kitchen to code, bring existing media room to code. 202105261139 · Gnetzer General Contractor | filed May 2021 · issued Sep 2024 · done Dec 2025 | $180k | city record |
| Revision | Revision to permit 202105261139 due to existing field conditions. Add new posts and beams to support roof deck. Omit previously permitted property line window. 202504083980 · cites 202105261139 · Gnetzer General Contractor | filed Apr 2025 · issued Oct 2025 · done Dec 2025 | $5,000 | city record |
| Electrical | 68-68a vienna st replace light ro new fixture. Installing a new circuit for kitchen. E20250225296 | Feb 25, 2025 → Oct 21, 2025 | — | |
| Plumbing | Relocate furnace. PM20250225757 | Feb 25, 2025 → May 23, 2025 | — | |
| Plumbing | Existing kitchen inspection. PP20250311026 | Mar 11, 2025 → Apr 3, 2025 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 5948, lot 007D
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.