Add new unit at basement and ground floor of exiting vacant commercial space with addition to 1st floor rear deck. Completed structural work under pa#s: 201706260347, 201804035334, 201808076592. Previous structural permits to be finaled with this permit application. Detached ADU under pa#:.

filed Mar 2022issued Oct 2024 · permit wait 2 years 7 monthscompleted Mar 2026 · built in 1 year 4 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$584,936 + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
2 years 7 months
filed → issued
Build time
1 year 4 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAdd new unit at basement and ground floor of exiting vacant commercial space with addition to 1st floor rear deck. Completed structural work under pa#s: 201706260347, 201804035334, 201808076592. Previous structural permits to be finaled with this permit application. Detached ADU under pa#:.
202203240803 · Nolan Construction INC
filed Mar 2022 · issued Oct 2024 · done Mar 2026$569kcity record
SprinklersResidential fire sprinkler system 13r existing expansion add 11 sprinklers 1st floor, add 14 sprnklers - basement. Ref pa 202203240803 ref sprinkler 202112073880.
202412176950 · cites 202203240803 · Madden Plumbing LLC
filed Dec 2024 · issued Jan 2025 · done Sep 2025$16kcity record
RevisionRevision 202203240803- to include add chase, move stairs and kitchen, shorten shearwall. No exterior work.
202502049624 · cites 202203240803 · Nolan Construction INC
filed Feb 2025 · issued Feb 2025 · done Mar 2026—city record
ElectricalNew electrical service new lighting and outlets throughout unit.
E202502109891
Feb 10, 2025 → Aug 28, 2025—
PlumbingInstallation of two centeral heater 96% efficiency flue pipe pvc for two furnace and flue pipe for a water heater.
PP20241113999
Nov 13, 2024—
PlumbingInstallation of two central heater 96% efficeincy flue pipe pvc for two furnace and flue pipe for a water heater.
PM20241113001
Nov 13, 2024 → Feb 26, 2026—
PlumbingWork category: 4pa; installation of overhead wet sprinkler system throughout basement and first floor. Connecting to existing supply.
PW20250107117
Jan 7, 2025 → Jan 9, 2025—
Plumbing4 bathrooms ( 4 toilets, 4 sinks, 2 tubs, 2 showers) 1 laundry, 1 water heater, sewage ejector, new kitchen, add new gas, new water main.
PP20250210460
Feb 10, 2025 → Feb 26, 2026—
4 other permits on this lot during the project, not counted
OtherTo obtain final inspection for work approved under pa# 2018-0403-5334. All work is complete.
202512182195 · Nolan Construction INC
filed Dec 2025 · issued Jan 2026 · done Mar 2026—city record
OtherTo obtain final inspection for work approved under pa# 2017-0626-0347. All work complete.
202512182202 · Nolan Construction INC
filed Dec 2025 · issued Jan 2026 · done Mar 2026—city record
OtherTo obtain final inspection for work approved under pa# 2018-0807-6592. All work is complete.
202512182205 · Nolan Construction INC
filed Dec 2025 · issued Jan 2026 · done Mar 2026—city record
OtherTo obtain final inspection for work approved under pa# 201608114832, 201609137568, & 201610079779. All work is complete.
202601294784 · Nolan Construction INC
filed Jan 2026 · issued Jan 2026 · done Mar 2026—city record

These permits also cite 201706260347, 201804035334, 201808076592, 201608114832, 201609137568, 201610079779, which the city filed before our records begin.

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 3996, lot 007